Migration strategy
Once the client is certain that the project will proceed, they should appoint a senior director responsible for moving, who can stand their ground under pressure from various elements of management who may fight their corner during the stress and upheaval of moving. The job is one that requires the skillful co-ordination of a multitude of time consuming tasks. On larger projects this is likely to require a team of people working under the director, including an accommodation manager and perhaps a facilities manager.
After preparing a policy for occupation, setting out how the facility will be used (see article on occupation), the director and their team should prepare a migration strategy (or move in programme) setting out the procedures for moving in such a way as to minimise disruption whilst allowing the efficient re-use of assets from any existing facilities.
This migration strategy might include:
- A detailed, phased, logistical programme for purchasing or moving of furniture and equipment.
- A detailed, programme for moving or recruiting staff.
- Requirements for the hire of temporary equipment.
- Removal contracts.
- Setting up a help desk with a rapid response team.
- Postal and information and communications technology (ICT) arrangements to ensure continuity of communication (including transfer of hardware).
- Setting up 'goods in' and 'dispatch' rooms, a post room and an information and communications technology support centre.
- Catastrophe planning for fire or flood.
- Staff transportation strategy.
- Parking allocation.
- Access by consultants, contractors and suppliers for summer and winter checks of building services systems and environmental conditions (which can only be properly carried out in a fully operational building).
- Room allocation.
- Signage.
- Catering facilities and environmental health approval of kitchen areas.
- Liaison with emergency services.
- Stocking and storage of goods and consumables.
- Communications between facilities during the move.
- Installation of existing equipment requiring electrical, drainage, extract or cooling services such as vending machines or fume cupboards.
- A risk schedule with mitigation measures (for example; the absence of key personnel, late building handover, alarm activation, interruption of power or water supply and so on).
The client may also need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
If the soft landings framework is adopted, there may be additional requirements to ensure a smooth transition from construction to occupation, and these should be included in appointment documents and contracts. See soft landings for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
IHBC’s response to Parliamentary Committee
On Levelling-Up and Regeneration Bill.
Finalists for 2022 CIOB Awards revealed
Over 70 managers and organisations shortlisted for the 14 awards.
Types of building sensors on BD
From biometric to electrical current, chemical and more.
Government mandates detectors in rented homes
Changes are due to come into force on 1st October 2022.
80% of major government projects are rated red or amber
Heed advice and insight of this report IPA tells the government.
The end of the games but continued calls for action
From the Commonwealth Association of Architects.
CIOB respond to the government call for evidence
For the Levelling Up, Housing & Communities Committee.
How are buildings and their occupants responding to extreme heat?
BSRIA's Technical Director reflects on recent weather patterns.
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.