Handover of the construction site to the client
Contents |
[edit] What is the handover stage in construction?
The handover stage it the stage of a construction project when the site is handed back to the client for them to occupy. This takes place once the contract administrator has confirmed that the works defined in the contract are complete (typically once practical completion has been certified).
As well as allowing handover of the site to the client, practical completion will also:
- Release half of the retention (an amount retained from payments due to the contractor to ensure they complete the works).
- End the contractor's liability for liquidated damages (damages that become payable to the client in the event that there is a breach of contract by the contractor - generally by failing to complete the works by the completion date).
- Signify the beginning of the defects liability period.
[edit] When can handover take place?
There is no absolute definition of practical completion and case law is very complex. There is some debate about when practical completion can be certified and whether it can be certified where there are very minor (de minimis) items 'not affecting beneficial occupancy' that remain incomplete.
It is important to note however, that the defects liability period, which follows certification of practical completion, is not a chance to correct problems apparent at practical completion, it is the period during which the contractor may be recalled to rectify defects which appear following practical completion. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
NB if the project is being completed in phases, the client may take possession of different parts of the site at different times. This can lead to complications with access procedures, security, noise an disturbance and so on.
For more information see: Partial possession and Sectional completion.
[edit] What is the handover procedure?
Handover should be planned well in advance, and any special requirements should be included in relevant appointment documents and contracts. See: Handover strategy for more information.
Handover may take place during a handover meeting following an inspection of the site.
During handover the client should be issued with:
- Keys, fobs and transmitter controls for the development.
- The health and safety file.
- The draft building owner's manual.
- The building log book.
- A building user's guide.
- Up to date testing and commissioning data.
- All certificates and warranties in respect of the works.
- As-built drawings from consultants and specialist suppliers and contractors (or as manufactured and installed), or an as-constructed building information model.
- Copies of statutory approvals, waivers, consents and conditions.
- Equipment test certificates for lifts, escalators, lifting equipment, cradle systems, boilers and pressure vessels.
- Licences such as licences to store chemicals and gases and to extract groundwater from an artesian well.
If building information modelling (BIM) is being used, the common data environment may be transferred to the employer, including the final published information and the archive which provides a record of all activities in the common data environment during the project. If they have not already done so, the employer should appoint an asset information manager to maintain the information.
In addition:
- A defects reporting procedure should be agreed.
- Access arrangements should be arranged for the contractor to rectify defects.
- The contractor’s insurance cover ceases upon practical completion so a new policy for full cover needs to be put in place.
- The contractor will no longer be responsible for security and so the client's own security arrangements need to be implemented.
- As the client's facilities management team takes over the running of plant and equipment. Meters and fuel should be checked and recorded and tools and spares issued or sourced.
- Legal agreements such as adoption of roads or lease agreements should be signed.
- Outsourced contracts for maintenance should be signed.
If a soft landings procedure has been adopted, there may be additional requirements to ensure a smooth transition from construction to occupation, such as aftercare services and the provision of a technical guide. These additional services should be included in appointment documents and contracts. See Soft landings for more information.
NB The RIBA Plan of Work 2020 renamed stage 6 'handover and close out' as 'handover. The Plan of Work suggest that: 'In addition to the core contractual obligations to rectify defects, certify Practical Completion and close out the Building Contract, other tasks need to be undertaken. A Project Performance session needs be facilitated, so that the project team can share their experiences for the benefit of future projects... Initial Aftercare tasks need to be initiated and completed.'
[edit] Related articles on Designing Buildings
- BREEAM Handover.
- BSRIA updates Handover and O&M manuals.
- Building completion.
- Building owner's manual.
- Building log book.
- Building manager.
- Client commissioning.
- Completion.
- Defects liability period.
- Difference between practical completion and partial possession.
- Early use.
- Extended aftercare.
- Handover and close out.
- Handover plan.
- Handover strategy
- Health and safety file.
- Initial aftercare.
- Practical completion.
- Soft landings.
- Soft Landings for owners.
- Whole life costs.
[edit] External references
- BSRIA Handover, O&M Manuals, and Project Feedback. A toolkit for designers and contractors.
Featured articles and news
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Great introduction with links to lots of other articles giving more detailed information.