Initial aftercare for completed construction works
The soft landings framework is a joint initiative between BSRIA (Building Services Research and Information Association) and UBT (Usable Buildings Trust). It is an open-source framework that is intended to ‘…smooth the transition into use and to address problems that post-occupancy evaluations (POEs) show to be widespread’ (ref Useable Buildings Trust).
The government considers that soft landings sits alongside Building Information Modelling (BIM), as BIM feeds facility management systems and helps enable future alterations to completed buildings. As a result, it is thought that in parallel to the roll out of BIM, the government may mandate a Government Soft Landings (GSL) handover protocol for central government projects by 2016.
Soft landings includes provisions for initial aftercare and extended aftercare services for three years after the completed development has been handed over for occupation. A decision to require this aftercare should be made early during the development of the project so that the necessary services can be included in tender documents and appointment agreements.
The initial aftercare period is intended to deal with immediate problems, help the occupants understand the development, and help facilities managers learn to operate it. This is a period of intensive aftercare that will typically last 4 to 6 weeks, but may be longer for complex buildings such as hospitals and shorter for simple buildings such as shops. After this, the aftercare on site will reduce, although periodic reviews will continue.
A visible and accessible soft landings team, including members of the design and construction team, should be stationed on site to receive feedback, fine tune systems and ensure proper operation of the completed development. The architect will often be the main point of contact for occupants during this period, although queries most commonly relate to the operation of building services systems, and so the they will need good access to other members of the project team.
Aftercare meetings may be held with building users to explain how the building operates, answer questions and obtain feedback. The aftercare team may also disseminate information about problems that have been encountered, and progress that has been made, perhaps by issuing fortnightly newsletters.
There may be regular ‘walkabouts’ to assess operational performance and obtain data, and there will be specific meetings with facilities managers to explain systems operation in detail and obtain feedback.
This process also provides the opportunity for the project team to learn about problems that have been encountered, assess what steps might be taken to rectify them and consider how to avoid them on future projects.
The initial aftercare period will be followed by extended aftercare during years 1-3, when outstanding issues are resolved and post occupancy evaluations are fed-back for future projects. In year 1, problems are identified, training provided and systems fine-tuned, with regular reviews. In years 2 and 3, performance is reviewed, and post occupancy surveys carried out, but with reviews becoming less frequent.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- BIM and facilities management.
- BREEAM Aftercare support.
- Building information modelling.
- Building log book.
- Building owner's manual.
- Building users guide.
- Building performance metrics.
- Client commissioning.
- Defects liability period.
- Extended aftercare.
- Government construction strategy.
- Handover to client.
- Lessons learned report.
- Medical Research Council Laboratory of Molecular Biology soft landings project.
- Migration strategy.
- Occupation of completed construction site.
- PAS 1192-2:2013
- Post occupancy evaluation.
- Post project review.
- Performance in use.
- Snagging.
- Soft landings.
- Soft Landings for owners.
- Technical guide.
Featured articles and news
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.