Breach of contract
If one of the parties to a contract fails to perform as required, this may constitute a breach of contract. A breach may entitle the innocent party to make a claim for damages for the losses it has suffered.
If the breach of contract is serious (a material breach), then the innocent party may also consider that it is discharged from any further obligations under the contract.
If the breach is less serious, (a non-material breach, sometimes referred to as a default) the innocent party may make a claim for damages, but may not consider it is discharged from any further obligations under the contract. This prevents the innocent party from excusing their own performance because of a minor breach of just one part of the contract.
This is generally the position on construction contracts, where some works are likely to have been carried out, but one or more may remain undone, incomplete or defective. As building contracts are usually divided up into parts (divisible), and include a series of separate payments, this sort of partial failure would not allow the innocent party to excuse their performance, i.e. a failure in one part will generally only mean that the innocent party is not liable to pay for that part. Furthermore, if the works have been substantially performed, then they must pay for them subject to a claim for the parts that have not been performed.
On construction contracts, it is generally in the interests of both parties for the contract to continue and for the works to proceed irrespective of minor problems. Whilst damages for breach of contract may seek to put the innocent party in the position it would have been in had there not been a breach of contract, the delay and disruption caused, for example, by having to appoint a new contractor can far outweigh the difficulties of proceeding, albeit under difficult circumstances.
Construction contracts generally make provisions for the contract to be varied without there being a breach. Variations, extensions of time, claims for loss and expense, liquidated damages, and the defects liability period all provide for the contract to be varied or for problems to be rectified.
Where one party behaves in such a way that it indicates it no longer intends to accept its obligations under the contract, this is considered to be a repudiatory breach (or fundamental breach), allowing the innocent party to terminate the contract and to sue for damages. Generally the contract will set out what those breaches are, but they might include:
- Refusal to carry out work.
- Abandoning the site.
- Removing plant from the site.
- Failure to make payments.
- Employing others to carry out the work.
- Failure to allow access to the site.
- Failure to proceed regularly and diligently.
- Failure to remove or rectify defective works.
Where repudiation is considered to have occurred, the innocent party can either affirm that the contract will continue or accept the repudiation and so terminate the contract. In either case, they will have the right to claim damages. Either way, it is important that there is some sort of response, as inaction may be considered to be an affirmation of the contract.
Assessing the seriousness of breaches of contract depends on the particular circumstances and terms of the contract. For example, if a contractor failed to carry out the work to an agreed timetable, this might be considered a relatively minor issue on some projects, whilst on others it could be an extremely serious breach. The innocent party must be careful therefore to establish that there has actually been a material breach before considering that the contract is terminated, otherwise they might find themselves in breach of contract.
This can lead to disputes, where for example, the client refuses to make payment, claiming that the contractor has failed to perform, whereas the contractor contends that they are not performing because the client has refused to make payment.
An anticipatory breach (or anticipatory repudiation) occurs when one of the parties to the contract declares to the other that they do not intend to perform their obligations under the contract.
The contract may also allow termination under other circumstances, such as frustration or insolvency. It may also allow termination for ‘convenience’, but this may leave the terminating party open to significant claims by the other party. See: Termination for more information.
Rescission is a process of returning both parties to the position they would have been in had they not entered into the contract. This might be appropriate for example if there is a serious error in the contract.
The term irremediable breach refers to a situation where there is a defect in the works for which the cost of rectification is unreasonable relative to the nature of the defect. Under these circumstances the contract administrator may issue a certificate of making good defects, with a deduction relative to the amount by with the value of the works has been reduced by the defect.
NB: The Construction Act now gives contractors the right to suspend performance for non-payment.
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution.
- Breach.
- Causes of construction disputes.
- Civil procedure rules.
- Concurrent delay.
- Construction Act.
- Contract claims.
- Defects.
- Dispute resolution boards.
- Extension of time.
- Fair payment practices.
- Frustration.
- Housing Forum seeks unity over suspension of works.
- Injunction.
- Legal action.
- Litigation.
- Liquidated damages.
- Liquidated v unliquidated damages.
- Loss and expense.
- Material breach.
- Non-material breach.
- Pre-action protocol for debt claims
- Remoteness.
- Repudiation.
- Subletting.
- Termination.
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.






















