Possession of the site by the contractor
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see Handover to client).
The contract may state the date for possession of the site by the contractor (or commencement date), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
If the client fails to give possession of the site to the contractor, and there are no provisions for delay in the contract, then they will be in breach of contract. Even if the contract does provide for delay in giving possession of the site to the contractor, the contractor will still be able to claim for an extension of time and perhaps loss and expense.
A formal handover meeting when the contractor takes possession of the site is an opportunity to:
- Handover keys.
- Discuss issues related to continued occupation of any part of the site (particularly on refurbishment projects) such as access.
- Discuss security.
- Issue any significant information about the site (such as site services, tree preservation orders, etc.).
- Discuss ongoing maintenance, operation and protection issues regarding existing structures, landscape or other features to be retained.
- Discuss noise and dust reduction measures.
- Verify insurance provisions.
- Read meters.
- Provide contact details for key personnel on both sides.
- Discuss access for client's personnel and representatives or other client contractors.
See also Pre-contract meeting. The pre-contract meeting is an important meeting that takes place after the contractor has been appointed but before work commences on site. It is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage.
On certification of practical completion, the contractor will give possession of the site back to the client (see Handover to client).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.