Deferment of possession
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see handover to client). The contract may state the date for possession of the site by the contractor (sometimes called the 'commencement date'), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
Some contracts (such as the JCT Standard Form of Building Contract) will entitle the client to defer giving the contractor possession of the site for a period of up to six weeks unless a shorter period was stipulated in the contract particulars (it is probably unwise to reduce the period). This provision enables the client to defer possession without being in breach of contract.
It is considered that deferment of possession is a positive activity which the employer should signal by giving written notice although that is not expressly stated.
Deferment of possession can be considered a relevant matter, giving rise to the possibility of the contractor claiming an extension of time or loss and expense. However, for such a claim to succeed, the deferment must have a material effect on the regular progress of the works. Obviously, deferment will have an immediate effect on progress, however, it does not extend the contract period, it simply moves it in time with dates for possession and completion which continue to have the same relationship to each other.
If the contractor is given early notice of deferment, they are likely to incur far fewer costs than if the deferment is only notified a few days before start on site. Issues that might be considered include:
- Plant hire.
- The possibility of using operatives elsewhere.
- Delivery dates
- Key dates for sub-contractors
- The possibility of increased costs and interest charges.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A sun, tide, mass or scratch dial.
A brief description of time in the sun.
ICE Trustee Board update June 2022
Given by ICE President Ed McCann.
Artificial intelligence and project management
Two new research reports published by APM.
Association for Project Management membership offer
50% off APM Associate membership for Designing Buildings users.
Building safety, a shifting landscape for professionals
A commentary from the insurance perspective.
In brief with further links.
Walter Segal: self-built architect
A definitive book on a pioneer of green architecture.
Funding for heritage on the high street
Using heritage as a catalyst for reviving historic centres.
Commonwealth Heads of Government Meeting update.
Declaration prioritising sustainable urbanisation adopted.
A small hidden, often distant but key building component.
Some brief words about the actuator.
CIAT Chief Executive steps down.
After 34 years at the Institute.
Volunteer opportunity launched by the ICE
To support the next generation of engineers.
Provisional findings show illegal cartels in the industry.
CIAT reporting from the Competition and Markets Authority.
Making sustainable construction number one priority.
The future of construction report.
Interview with ECA CEO.
Many provisions came into force on June 28, 2022.
With room to expand.
An information packed session at the BSRIA conference.
Refurbishment, Energy Efficiency, Indoor air and process.
Create a profile, write informed product articles and share.
Aluminium Composite Panels (ACP) is one example.
We are indeed now 10 years old, so go on and be bold !
Write about something you know, help us build and grow !