Reasonable time
If the parties to a contract or agreement have not established a specific timescale within which things must happen, the law may apply the concept of ‘reasonable time’. In that case, any time that is not manifestly unreasonable in those circumstances may be termed ‘reasonable time’. It is the time that the law considers reasonable under the specific contract for undertaking whatever is required and which is deemed necessary – and can be undertaken conveniently – as soon as circumstances permit.
The concept of reasonable time may also be applied to making a payment, accepting an offer or, for example, to a landlord who may be required to make property repairs within a reasonable time.
English law frequently requires things to be done in reasonable time but ‘reasonable time’ is never defined. The acceptable period for any particular case brought before the law may be established by referring to trade practice, custom or where there are similar precedents.
Due to its subjective and vague nature, the term causes controversy and problems in many court cases. People may argue for a variety of time frames which, while not unreasonable, are nevertheless not in alignment with a court’s decision.
Reasonable time may also be applied in a ‘time at large’ situation which may occur when a client is responsible for delaying construction works but the contract does not allow for an extension of time to be granted. In that case, time would be ‘at large’, the client would not be able to claim liquidated damages from the contractor who would then only have to complete the works in a ‘reasonable time’. See ‘time at large’ for further information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.