Contract programme
Constructing a building is a complex process which involves the co-ordination of many multifaceted resources. To ensure the project achieves the requisite time and budgetary constraints, detailed programmes are devised to eliminate.
There are several areas of work that require detailed planning, one of which is the contract programme. Typically, the successful contractor will start planning the project in great detail as soon as they have signed the construction contract. It is usually the contractor’s responsibility to specify the order in which the work will be undertaken. This will require a close examination of what resources are available, assessing the time that may be required and the impact that subcontractors, suppliers and other third parties will have on the programme.
Using the information in the contract documents, the contractor usually prepares a method statement in the form of a schedule that divides the intended construction work into operations; this will encompass the labour and plant requirements – and their availability – associated with each work element. This information is then converted into a draft programme and circulated to all management personnel associated with the project. Once they have had enough time to consider the proposals, they can discuss the contents so that working methods and amendments can be agreed.
Time overruns are common in construction projects and contractors will try to avoid this happening by ensuring the work is completed earlier than the target completion date. This will be particularly pertinent if the contract involves the imposition of liquidated and ascertained damages after the agreed completion date.
The nature of the construction process means that a planned programme can also become unrealistic due to factors beyond the contractor’s control, such as inclement weather, materials delivered later than agreed, the client or designers giving late instructions and so on. If such circumstances occur, the contract programme should be updated to reflect the situation and include a revised action plan.
The co-ordination of material and component deliveries, subcontractor and trade work can be portrayed in visual representations based on the critical path method (CPM) and produced by complex software programmes. The CPM can provide an accurate reflection of site operations and the interrelationships between activities.
For more information see: Critical path and Programme for building design and construction.
Some forms of construction contract will require the prepartion of a programme by the contractor. For example NEC requires that the contractor prepares a programme for the works which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use.
For more information see: Accepted programme.
Other forms of contract may require that the contractor provides a master programme for the construction of the works as soon as possible after the execution of the contract, if it has not been previously provided. However, as it is produced after the execution of the contract, the programme does not impose any obligation on the contractor beyond those obligations imposed by the contract documents.
For more information see: Contractor's master programme.
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Construction progress report.
- Construction stage report.
- Contractor.
- Contract administrator.
- Contractor's master programme.
- Critical path method CPM.
- Earned value analysis.
- Gantt chart
- How progress is agreed in construction.
- Long lead-time item
- Programme consultant.
- Project programme.
- Progress of construction works.
- Scheduling construction activities
.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.

























