How progress is agreed in construction
Contents |
[edit] Introduction
Agreeing how much progress has been made at various stages or a construction project ensures the main parties to the contract are aware of how the programme is proceeding, it can assist in calculating payments due, and it can help identify potential difficulties and avoid delays and disputes.
There are a number of ways in which progress can be assessed and reported.
[edit] Project programmes
Programmes describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time. They will typically identify:
- The start date, completion date and the date the programme was prepared.
- Dates and durations allocated to specific tasks.
- A critical path.
- Tasks which can only be carried out after other tasks have been completed.
- Tasks which can be carried out simultaneously.
- 'Float' within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path).
- The need for specific resources such as plant, services or materials and their lead time.
Programmes do not normally form part of the contract documents, but rather are indicative tools for administering the project and helping to agree progress.
Contracts may require that the contractor provides a master programme for the construction of the works, but again, as this is produced after the execution of the contract, it does not impose any obligation on the contractor beyond those obligations already imposed by the contract documents.
For more information see: Project programme and Contractor's master programme.
[edit] Contractual obligations
Some contracts (such as the New Engineering Contract) may include key dates by which specific milestones or conditions must be met, and the contractor may have a duty to give early warning of anything that may delay the works. The contractor may also be under an obligation to proceed ‘regularly and diligently’ with the works.
[edit] Progress meetings
Progress will typically be assessed at regular construction progress meetings, attended by the contractor and the consultant team, providing an opportunity to:
- Receive progress reports from the contractor (the contractor may also hold progress meetings with sub-contractors and suppliers prior to the construction progress meeting).
- Receive progress reports from the consultant team.
- Receive cost reports from the cost consultant.
- Receive records of sub-contractors and labour on site.
- Receive progress photos.
Progress meetings typically generate a construction progress report for the client.
For more information, see Construction progress meeting and Construction progress report.
[edit] Interim payments.
The Housing Grants, Construction and Regeneration Act stipulates that interim or stage payments are due to any party to a construction contract that has a duration of more than 45 days. Therefore, almost all constructions contain provisions for interim payments.
Contracts should also include clauses that detail:
- The valuation method for payments.
- Criteria under which interim payments will be made.
- Payment timings.
- Administrative rules to which those undertaking the valuation should adhere.
The basis of the valuing interim payments will vary depending on the terms of the contract, but may include:
- Activity schedules assessed in terms of percentage achieved or completion of each activity.
- Milestones reached on a pre-agreed programme.
- Measurement against a bill of quantities.
- Stage payments against calendar dates.
For more information see: Interim valuation.
[edit] Key performance indicators
Key performance indicators (KPIs) are measurable values that can be used to assess how effectively a project, or part of a project are performing. This might include project progress.
Where key performance indicators are to be used on a project, it is important that they are identified in tender documentation and that the regular provision of the information required to assess them is a requirement of the contract. This may be of particular importance where the contract stipulates that the contractor will be rewarded or penalised based on their performance relative to certain indicators.
For more information, see Key performance indicators.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.