Construction progress meeting
During the construction stage, the contract administrator (sometimes referred to in different forms of contract as the 'architect/contract administrator', 'project manager', 'engineer' or 'employer's agent') holds regular (often monthly) construction progress meetings attended by the contractor and if necessary members of the consultant team.
The client, client representative or project manager may also wish to attend these meetings. Construction progress meetings may require decisions to be made and so it is important that they are attended by sufficiently senior individuals if delays are to be avoided.
Construction progress meetings are an opportunity to:
- Receive progress reports from the contractor (the contractor may hold a progress meeting, sometimes called a production meeting, with sub-contractors prior to the construction progress meeting).
- Receive progress reports from the consultant team.
- Receive cost reports from the cost consultant.
- Receive records of sub-contractors and labor on site.
- Receive progress photos (which may be required from the contractor if included in the preliminaries, or may sometimes be commissioned separately by the client).
They are also an opportunity to discuss major issues raised, such as:
- Any special circumstances which may affect the contract at any stage.
- Testing regimes.
- Mock-ups.
- Quality issues.
- Weather reports.
- Issues that may impact on costs.
- Health and safety issues.
- Issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety, etc.).
- Off-site fabrication and off-site payments.
- Earned value analysis.
- Design issues.
- Warranties.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
Meeting minutes should be prepared, with a requirement that any disagreement with the items recorded in the minutes is raised within a pre-defined period (perhaps one week). The progress meetings will also result in the preparation of a construction progress report for the client.
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however, they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
On large projects, the construction manager may hold a daily logistic meeting on site with trade contractor foremen to organise, schedule and co-ordinate on-site shared services such as deliveries and off-loading, hoists and craneage, scaffolding, safety issues, rubbish clearance, etc.
Similar meetings may be held on management contract projects between the management contractor and the works contractors.
[edit] Related articles on Designing Buildings Wiki
- Adapting your technology to the new working normal.
- Client.
- Construction manager.
- Construction progress report.
- Construction stage report.
- Contractor.
- Contract administrator.
- Consultant team.
- Earned value analysis.
- Employer's agent.
- Five steps towards a successful construction project.
- Health and Safety.
- How progress is agreed in construction.
- Management contractor.
- Project programme.
- Progress of construction works.
- Project manager.
- Samples and mock-ups.
- Site meeting.
- Sub contractor.
- Works contractors.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.

















