Construction process
The ‘construction process’ (sometimes called the ‘construction stage’) is the physical processes of building, landscaping or refurbishing plus all the associated activities, such as demolition, site clearance, administration and so on.
Construction works are typically carried out by contractors, although in the housing sector, contractors may be referred to as builders or housebuilders, and contractors may appoint subcontractors and other suppliers to carry out some or all of the works.
The process may start, following a procurement process, with handover of the site from the client to the contractor and end with handing back a completed project to the client. It does not include pre-construction activities such as preparation of the brief, forming a design team or design and so on, although these activities may be carried out at the same time as construction.
The following processes can form part of the construction process:
- Mobilisation.
- Demolition.
- Site clearance.
- Erection of hoardings, welfare facilities and so on.
- Setting out.
- Excavation.
- Installation of foundations.
- Frame construction.
- Cladding installation.
- Fitting out.
- Landscaping and highways.
See Construction works for more information.
In terms of the work stages of the RIBA Plan of Work, the construction process can be said to start at stage 5 and finish at the end of stage 6, as shown below.
- 0 - Strategic definition.
- 1 - Preparation and brief.
- 2 - Concept design.
- 3 - Developed design.
- 4 - Technical design.
- 5 - Construction.
- 6 - Handover and close out.
- 7 - In use.
The site is generally handed back to the client after certification of practical completion. This followed by a defects liability period, during which any defect that become apparent may be rectified by the contractor. There is some debate about when practical completion can be certified and whether it can be certified where there are very minor (de minimis) items 'not affecting beneficial occupancy' that remain incomplete. For more information see: Practical completion.
The contractor may still be liable for damages, for breach of contract, or for negligence after the defects liability period if latent defects become apparent. See Latent defects for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Myths and top tips.
CLC plans to ease impact of construction inflation.
BG 50 & VDI 2035 – your questions answered.
Types of domestic heating systems.
Will the way we heat homes change when winter comes ?
Extended reality in a post-pandemic world.
Can XR technology be leveraged in design & construction?
Or are you capping.
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.