Latent defects
It is the nature of construction projects that faults and defects caused by failures in design, workmanship or materials, may not become apparent or readily detectable (even with the exercise of reasonable care) until many years after completion of the project, long after the end of the defects liability period. Such defects are known as latent defects (as opposed to patent defects which are apparent).
Examples of common latent defects include:
- Defective basement tanking allowing water penetration.
- Inadequate wind-posts or wall ties causing movement damage to walls.
- Under-strength concrete or misplaced reinforcement allowing movement damage to the structure.
- Inadequate foundations causing subsidence of the building.
It is also a feature of construction projects that the completed building will have a life-cycle of many years often with a succession of future owners who had no involvement in the original construction, but who have a liability to maintain the structure.
After the end of the defects liability period the building owner does not have a contractual right to insist that the contractor rectifies defects not notified during that period (as will often be the case with latent defects). The building owner must instead seek redress in an action for damages, for breach of contract, or for negligence. In the case of dwellings there is a statutory remedy provided by the Defective Premises Act 1972.
These rights of action are not perpetual; actions for breach of contract are time barred after 6 years from the date of breach (usually the completion of the building although with a failure of design the breach may occur earlier) see the Limitation Act 1980 Section 5. For a contract under seal, the period is 12 years (see the Limitation Act 1980 Section 8). Clearly therefore it is important to the building owner that all contracts are made under seal; not so for the contractor, the professional consultant or their insurers. Where the claim is for negligence, the time limit is six years from the date on which the cause of action accrued, which will be the date when the damage occurred.
Complex arguments arise in respect of economic loss. This may be many years after the completion of the building. The provisions of the Latent Damage Act 1986 Section 1 (by way of a new Section 14A to the Limitation Act) provides a limitation period for negligence of 3 years from the first knowledge of the cause of action and (by way of a new section 14B to the Limitation Act) an overriding 15 year long-stop from the act of negligence giving rise to the damage. Section 3 of the Act is important as it gives a new cause of action to successive owners.
Commercial fixes for latent defects and successive owners include, collateral warranties, guarantees, building warranty schemes and latent defects insurance. Latent defects insurance first appeared in the UK in the 1980s, imported from Europe and known as decennial insurance. It soon fell out of favour as a result of being over-hyped and overpriced. Latent defect insurance is now making a comeback.
[edit] Related articles on Designing Buildings
- Caveat emptor.
- Certificate of making good defects.
- Collateral warranties.
- Damage caused by construction works.
- Defective Concrete Blocks Grant Scheme.
- Defects liability period.
- Defects.
- Design liability.
- Defects list.
- Final certificate.
- Flooring defects.
- Guarantees.
- Ground heave.
- Inspection.
- Making good.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Professional consultant's certificate.
- Professional indemnity insurance.
- Pyrite and mica redress issues in Dail Eireann.
- Retention.
- Settlement.
- Site inspector.
- Soft landings.
- Using satellite imagery to monitor movements in megaprojects.
- Why do buildings crack? (DG 361).
[edit] External references
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
Is it not time to look at a new model for regulating the construction industry. The need to identify the cause of the defect is essential as only then can the correct response to applied. There is a current model which is used in another industry which could be applied to the construction sector and it would make individuals accountable for their work and ensure a better product reached the market.