Contracts under seal v under hand
Contents |
[edit] Introduction
Contracts may be executed under seal (signed by the parties, witnessed and most importantly made clear that it is executed as a deed - see below) or under hand (a 'simple contract' that is just signed by the parties).
[edit] Consideration and limitation periods
There are two important differences between simple contracts, and contracts that are under seal (deeds):
Firstly, simple contracts and contracts under seal have different limitation periods. An action founded on a simple contract cannot be brought after six years from the date on which the cause of the action accrued. The limitation period for a contract under seal is 12 years.
Secondly, unlike a simple contract, a contract under seal does not have to be supported by valuable consideration.
For example, where a collateral warranty consists of unilateral undertakings by one party, the contract must be a contract under seal if it is to be enforceable. It is important to note that whilst consideration is not necessary for a contract under seal in the absence of valuable consideration and, arguably, in the absence of something more than mere nominal consideration, the remedy of specific performance will not be available in respect of the contractual undertakings (see Milroy v Lord).
Specific performance is an equitable remedy requiring the contract breaker to fulfil their contractual obligations, rather than awarding damages for breach. Equity does not assist a volunteer, hence the need for consideration. It is suggested that a deed, which relies on merely nominal consideration, could be rescued by the addition of a consideration, which consists of ‘the mutual undertakings’ of the parties to a deed.
[edit] Legislation
Much of the law relating to the execution of deeds was swept away on 31 July 1990 by the Law of Property (Miscellaneous Provisions) Act 1989 dealing with the execution of deeds by individuals, and by the Companies Act 1989 dealing with the execution of deeds by companies.
Section 1(3) of the Act provides that a deed must be signed by the person who is to be bound and the signature must be attested by a witness. If this procedure is not followed then the document will not be valid as a deed.
Section 1(2)(a) provides that a document shall not be a deed unless it is made clear on its face that it is intended to be a deed by the person making it. It follows that the document must be described as a deed and the attestation clause must include a statement that it is being executed as a deed. If such descriptive words are not included then the document will not be valid as a deed.
The Act does not abolish the old common law rule that to be effective a deed must be delivered by the person who is to be bound. Delivery does not mean the physical handing over of the document but the evincing of an intention, whether by words or conduct, that the party is to be bound. Such intention was satisfied prior to the Act by signature and it is submitted that signature will continue to satisfy the requirement of delivery.
Companies may still use their seals to execute a deed provided that this is in accordance with their Articles of Association. Section 130 of the Companies Act 1989 introducing a new section 36(a) to the Companies Act 1985 provides by sub-section 4 that if a document is signed by a director and the secretary of the company or by two directors of the company and is expressed (in whatever form of words) to be executed by the company it will have the same effect as if it had been executed under the common seal of the company, i.e. a deed.
Further, sub-section 5 provides that a document which makes it clear on its wording that it is intended to be a deed has the effect of a deed even though the specific requirements for execution dealt with in sub-section 4 above are not complied with. For example, a document that is described as a deed and is executed by one director of the company will operate as a deed. Extreme care must be taken to ensure, if it is intended only to create a simple contract, that a company giving a collateral warranty does not accidentally execute the document in such a manner as to give rise to a deed.
[edit] Related articles on Designing Buildings
- Articles of agreement.
- Breach of contract.
- Causes of construction disputes.
- Collateral warranties.
- Contract claims.
- Construction contract.
- ESignatures.
- Engrossment.
- Letter of award.
- Litigation.
- Technology and Construction Court.
- Title.
[edit] External references
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.