Opening up works for inspection and testing
Construction contracts generally make provision for the contract administrator to instruct that inspections are carried out and that tests are undertaken on completed work where they suspect that there may be defects. They may carry out these tests themselves, or can have them carried out by third parties.
If those works have already been covered up, then this may require that they are opened up for inspection and testing, and clearly this may involve some cost and disruption for the contractor.
Where works are opened up, and tests reveal that there was no defect, then this may constitute a ‘relevant event’ and could entitle the contractor to an extension of time, and an addition may be made to the contract sum to pay the contractor’s costs, unless there was a requirement for the inspection or test to be carried out in the contract.
If a defect is revealed, the contractor must rectify it at their own cost.
Where a defect is revealed, and the contract administrator has reasonable cause to believe there may be other, similar defects (for example, a defect in the installation of insulation in one area may suggest there are similar defects elsewhere), they may issue further instructions for more of the works to be opened up. The contractor is not generally entitled to any adjustment of the contract sum or the completion date for these further tests, even if no further defects are found.
Similar provisions may exist in subcontracts allowing the contractor to instruct that subcontractors open up works for inspection and testing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Building regulations inspection.
- Building sector failing on supervision.
- Certificate of making good defects.
- Decennial liability.
- Defects.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects liability period.
- Delay damages.
- Design liability.
- Desktop study.
- Dilapidations.
- Fit for purpose.
- Inspection.
- Latent defects.
- Patent defects.
- Practical completion.
- Remedial work.
- Scaffold register.
- Schedule of defects.
- Site inspector.
- Site inspection.
- Testing construction materials.
[edit] External references
- Out-law - Defective work in construction projects
- ‘The JCT 05 Standard Building Sub-contract’, BARNES, P., Blackwell Publishing (2006)
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.






















