Opening up works for inspection and testing
Construction contracts generally make provision for the contract administrator to instruct that inspections are carried out and that tests are undertaken on completed work where they suspect that there may be defects. They may carry out these tests themselves, or can have them carried out by third parties.
If those works have already been covered up, then this may require that they are opened up for inspection and testing, and clearly this may involve some cost and disruption for the contractor.
Where works are opened up, and tests reveal that there was no defect, then this may constitute a ‘relevant event’ and could entitle the contractor to an extension of time, and an addition may be made to the contract sum to pay the contractor’s costs, unless there was a requirement for the inspection or test to be carried out in the contract.
If a defect is revealed, the contractor must rectify it at their own cost.
Where a defect is revealed, and the contract administrator has reasonable cause to believe there may be other, similar defects (for example, a defect in the installation of insulation in one area may suggest there are similar defects elsewhere), they may issue further instructions for more of the works to be opened up. The contractor is not generally entitled to any adjustment of the contract sum or the completion date for these further tests, even if no further defects are found.
Similar provisions may exist in subcontracts allowing the contractor to instruct that subcontractors open up works for inspection and testing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Building regulations inspection.
- Building sector failing on supervision.
- Certificate of making good defects.
- Decennial liability.
- Defects.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects liability period.
- Delay damages.
- Design liability.
- Desktop study.
- Dilapidations.
- Fit for purpose.
- Inspection.
- Latent defects.
- Patent defects.
- Practical completion.
- Remedial work.
- Scaffold register.
- Schedule of defects.
- Site inspector.
- Site inspection.
- Testing construction materials.
[edit] External references
- Out-law - Defective work in construction projects
- ‘The JCT 05 Standard Building Sub-contract’, BARNES, P., Blackwell Publishing (2006)
Featured articles and news
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherit assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.

















