Opening up works for inspection and testing
Construction contracts generally make provision for the contract administrator to instruct that inspections are carried out and that tests are undertaken on completed work where they suspect that there may be defects. They may carry out these tests themselves, or can have them carried out by third parties.
If those works have already been covered up, then this may require that they are opened up for inspection and testing, and clearly this may involve some cost and disruption for the contractor.
Where works are opened up, and tests reveal that there was no defect, then this may constitute a ‘relevant event’ and could entitle the contractor to an extension of time, and an addition may be made to the contract sum to pay the contractor’s costs, unless there was a requirement for the inspection or test to be carried out in the contract.
If a defect is revealed, the contractor must rectify it at their own cost.
Where a defect is revealed, and the contract administrator has reasonable cause to believe there may be other, similar defects (for example, a defect in the installation of insulation in one area may suggest there are similar defects elsewhere), they may issue further instructions for more of the works to be opened up. The contractor is not generally entitled to any adjustment of the contract sum or the completion date for these further tests, even if no further defects are found.
Similar provisions may exist in subcontracts allowing the contractor to instruct that subcontractors open up works for inspection and testing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Building regulations inspection.
- Building sector failing on supervision.
- Certificate of making good defects.
- Decennial liability.
- Defects.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects liability period.
- Delay damages.
- Design liability.
- Desktop study.
- Dilapidations.
- Fit for purpose.
- Inspection.
- Latent defects.
- Patent defects.
- Practical completion.
- Remedial work.
- Scaffold register.
- Schedule of defects.
- Site inspector.
- Site inspection.
- Testing construction materials.
[edit] External references
- Out-law - Defective work in construction projects
- ‘The JCT 05 Standard Building Sub-contract’, BARNES, P., Blackwell Publishing (2006)
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).