Opening up works for inspection and testing
Construction contracts generally make provision for the contract administrator to instruct that inspections are carried out and that tests are undertaken on completed work where they suspect that there may be defects. They may carry out these tests themselves, or can have them carried out by third parties.
If those works have already been covered up, then this may require that they are opened up for inspection and testing, and clearly this may involve some cost and disruption for the contractor.
Where works are opened up, and tests reveal that there was no defect, then this may constitute a ‘relevant event’ and could entitle the contractor to an extension of time, and an addition may be made to the contract sum to pay the contractor’s costs, unless there was a requirement for the inspection or test to be carried out in the contract.
If a defect is revealed, the contractor must rectify it at their own cost.
Where a defect is revealed, and the contract administrator has reasonable cause to believe there may be other, similar defects (for example, a defect in the installation of insulation in one area may suggest there are similar defects elsewhere), they may issue further instructions for more of the works to be opened up. The contractor is not generally entitled to any adjustment of the contract sum or the completion date for these further tests, even if no further defects are found.
Similar provisions may exist in subcontracts allowing the contractor to instruct that subcontractors open up works for inspection and testing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Building regulations inspection.
- Building sector failing on supervision.
- Certificate of making good defects.
- Decennial liability.
- Defects.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects liability period.
- Delay damages.
- Design liability.
- Desktop study.
- Dilapidations.
- Fit for purpose.
- Inspection.
- Latent defects.
- Patent defects.
- Practical completion.
- Remedial work.
- Scaffold register.
- Schedule of defects.
- Site inspector.
- Site inspection.
- Testing construction materials.
[edit] External references
- Out-law - Defective work in construction projects
- ‘The JCT 05 Standard Building Sub-contract’, BARNES, P., Blackwell Publishing (2006)
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
















