Defects certificate
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration. The third edition, NEC3 was published in 2005.
According to NEC, a defect is ‘… a part of the works which is not as stated in the Works Information or not in accordance with applicable law or the accepted design.’
Until the defects date, there is an obligation on both the supervisor and contractor to notify each other as soon as they are aware of a defect. The defects date is the date until which the contractor is liable to rectify any defects and this is typically 52 weeks from the completion of the works.
At, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects in other standard forms of contract. Issuing the defects certificate triggers the release of any remaining retention, although if there are any remaining defects listed on the defects certificate, a withholding notice may be served and retention may continue to be held.
The defect correction period defines the maximum period within which the contractor must rectify a notified defect. Different defect correction periods can be specified for different types of defects. The only circumstances when the defects certificate might not be issued on the defects date is if a previously notified defect has a defects correction period that ends after the defects date, in which case it is issued on that later date.
If notified defects are not rectified within the defect correction period, they may be rectified by others and the cost reimbursed by the contractor.
The parties are permitted to agree that certain defects need not be rectified, and in this case the contractor must submit a quotation for reduced prices, an earlier completion date or both, and an adjustment is then made to the works information.
[edit] Related articles on Designing Buildings Wiki
- Aftercare manager.
- Certificate of making good defects.
- Certificates in the construction industry.
- Decennial liability.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Defects liability period.
- Defects.
- Defects correction period.
- Defects list.
- Delay damages.
- Defects date.
- Dilapidations.
- Fit for purpose.
- Guarantees.
- Inspection.
- Latent defects.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Reasonable skill and care.
- Remedial work.
- Schedule of condition.
- Schedule of defects.
- Scott schedule.
- Site inspection.
- Site inspector.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.