Contract sum
The contract sum is the price agreed with the contractor and entered into the contract. The agreed contract sum should be calculated and checked very carefully as errors are deemed to have been accepted by both parties.
However, the contract sum does not constitute a 'fixed price' even if the contract is described as a fixed price contract, a lump sum contract or a guaranteed maximum price contract. A truly fixed price would actually not be in the interests of the client as it would mean they could not make changes to the works, and would require that the contractor price risks over which they may have no control, and which might not arise.
As a result, contracts generally allow for the contract sum to be adjusted, for example:
- Variations.
- Fluctuations.
- Prime cost sums.
- Provisional sums.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to opening up works for inspection and testing.
- Loss and expense.
When the contract sum is adjusted, this adjustment should be taken into account in the valuation of subsequent interim certificates.
Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum at the end of the defects liability period so that the amount of the final payment to the contractor can be determined. The amount of the final payment is then set out in the final certificate (or final statement).
NB: It is possible for the final certificate to show that money is owed to the client, rather than due to the contractor.
Construction contracts may in fact not require the preparation of a final account, although they generally do require the contractor to provide all documents necessary for the adjustment of the contract sum within a specified time, and set out the time scale for, and consequences of, issuing the final certificate.
On contracts such as measurement contracts, the contract sum may not be known when the contract is entered into, but instead is calculated as the works progress based on some agreed method of measurement.
[edit] Related articles on Designing Buildings Wiki
- Accounting.
- Base date.
- Construction contract.
- Contract sum analysis.
- Difference between lump sum and measurement contracts.
- Escalation.
- Final account.
- Final certificate.
- Fluctuations.
- Hard costs v soft costs.
- Interim certificates.
- Opening up works for inspection and testing.
- Outturn cost.
- Payment schedule.
- Provisional sums.
- Right to payment.
- The difference between a prime cost and provisional sum.
- Variations.
- What is a final account.
[edit] External references
- JCT: Deciding on the appropriate JCT contract.
Featured articles and news
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.





















