Contract sum
The contract sum is the price agreed with the contractor and entered into the contract. The agreed contract sum should be calculated and checked very carefully as errors are deemed to have been accepted by both parties.
However, the contract sum does not constitute a 'fixed price' even if the contract is described as a fixed price contract, a lump sum contract or a guaranteed maximum price contract. A truly fixed price would actually not be in the interests of the client as it would mean they could not make changes to the works, and would require that the contractor price risks over which they may have no control, and which might not arise.
As a result, contracts generally allow for the contract sum to be adjusted, for example:
- Variations.
- Fluctuations.
- Prime cost sums.
- Provisional sums.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to opening up works for inspection and testing.
- Loss and expense.
When the contract sum is adjusted, this adjustment should be taken into account in the valuation of subsequent interim certificates.
Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum at the end of the defects liability period so that the amount of the final payment to the contractor can be determined. The amount of the final payment is then set out in the final certificate (or final statement).
NB: It is possible for the final certificate to show that money is owed to the client, rather than due to the contractor.
Construction contracts may in fact not require the preparation of a final account, although they generally do require the contractor to provide all documents necessary for the adjustment of the contract sum within a specified time, and set out the time scale for, and consequences of, issuing the final certificate.
On contracts such as measurement contracts, the contract sum may not be known when the contract is entered into, but instead is calculated as the works progress based on some agreed method of measurement.
[edit] Related articles on Designing Buildings Wiki
- Accounting.
- Base date.
- Construction contract.
- Contract sum analysis.
- Difference between lump sum and measurement contracts.
- Escalation.
- Final account.
- Final certificate.
- Fluctuations.
- Hard costs v soft costs.
- Interim certificates.
- Opening up works for inspection and testing.
- Outturn cost.
- Payment schedule.
- Provisional sums.
- Right to payment.
- The difference between a prime cost and provisional sum.
- Variations.
- What is a final account.
[edit] External references
- JCT: Deciding on the appropriate JCT contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.

















