Difference between lump sum and measurement contracts
Lump sum and measurement are both types construction contracts.
Under a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. This is a type of 'fixed price' contract, where the contractors agree to execute the works described in the contract for a total sum of money (the contract sum). Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
For more information see: Lump sum contract.
NB it should be noted that whilst lump sum contracts are often referred to as 'fixed price', there are generally mechanisms within the contract to allow the contract sum to be changed, for example if variations are made, or if there are provisions to account for inflation. For more information see: Fixed price contracts.
Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) are generally used in situations where the design (or type of work required) can be described in reasonable detail, but the amount required cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
Measurement contracts can allow an early start on site, before design is complete, and they can allow changes to be made to the works relatively easily. However, there is inevitably some risk for the client as the cost of the works is not known. In effect, the client is taking the risk for any ‘unknowns’, and whilst this can result in competitive prices from contractors, the level of uncertainty for the client means that measurement contracts are rare other than on civil engineering projects.
For more information see: Measurement contract.
[edit] Related articles on Designing Buildings
- Construction contract.
- Contract sum.
- The difference between admeasurement and construction management contracts.
- Fixed price contract.
- Lump sum contract.
- Lump sum contract - pros and cons.
- Measured term contract.
- Measurement contract.
- Procurement route.
- Remeasurement.
- Right to payment.
- Schedule of rates.
- Schedule of rates term contract.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.























Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.