Difference between lump sum and measurement contracts
Lump sum and measurement are both types construction contracts.
Under a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. This is a type of 'fixed price' contract, where the contractors agree to execute the works described in the contract for a total sum of money (the contract sum). Lump sum contracts are generally appropriate where the project is well defined when tenders are sought and significant changes to requirements are unlikely. This means that the contractor is able to accurately price the works they are being asked to carry out.
For more information see: Lump sum contract.
NB it should be noted that whilst lump sum contracts are often referred to as 'fixed price', there are generally mechanisms within the contract to allow the contract sum to be changed, for example if variations are made, or if there are provisions to account for inflation. For more information see: Fixed price contracts.
Measurement contracts (sometimes called ‘re-measurement’ or ‘measure and value’ contracts) are generally used in situations where the design (or type of work required) can be described in reasonable detail, but the amount required cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun. The contract sum for measurement contracts is not finalised until the project is complete. At this point it is assessed on based on re-measurement of the actual amount of work carried out.
Measurement contracts can allow an early start on site, before design is complete, and they can allow changes to be made to the works relatively easily. However, there is inevitably some risk for the client as the cost of the works is not known. In effect, the client is taking the risk for any ‘unknowns’, and whilst this can result in competitive prices from contractors, the level of uncertainty for the client means that measurement contracts are rare other than on civil engineering projects.
For more information see: Measurement contract.
[edit] Related articles on Designing Buildings
- Construction contract.
- Contract sum.
- The difference between admeasurement and construction management contracts.
- Fixed price contract.
- Lump sum contract.
- Lump sum contract - pros and cons.
- Measured term contract.
- Measurement contract.
- Procurement route.
- Remeasurement.
- Right to payment.
- Schedule of rates.
- Schedule of rates term contract.
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.