Remeasurement
Civil Engineering Procedure 7th Edition, published by the Institution of Civil Engineers in 2016, suggests that remeasurement (or occasionally re-measurement) is the:
…calculation of the actual quantities of work ordered on the contractors in order to certify the payment due to a contractor. Remeasurement is also known as measure-and-value’. |
There is a subtle difference between the term remeasurement and the term admeasurement, in that remeasurement refers to the entire process of measuring again the quantities of work undertaken, whereas admeasurement refers only to the difference between the estimated quantity and the actual quantity.
Remeasurement contracts, measurement contracts or measure and value contracts may be necessary on projects where the type of works required can be described in reasonable detail when they are tendered, but the amount cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun.
Instead of giving a firm price, rates are provided in the contractor’s tender, either as part of the priced approximate bill of quantities, or within a schedule of rates. Then the actual quantities of work carried out are measured and the tendered rates applied to those quantities. The contractor is paid for the actual work they have done. As a result, the quantities paid for may vary from the original estimates.
See Measurement contract for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Admeasurement.
- Bills of quantities.
- Construction contract.
- Contract sum.
- Cost reimbursable contract.
- Difference between lump sum and measurement contracts.
- Emerging cost contract.
- Force account work.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Measurement contract.
- Measured term contract.
- Procurement route.
- Quantum meruit.
- Schedule of rates
- Schedule of rates term contract.
- Tender.
- Unit rates basis of payment.
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.