Henry Boot Construction Ltd v Alstom Combined Cycles
The case of ‘Henry Boot Construction Ltd. v Alstom Combined Cycles’ [1999] set a precedent that contractor’s rates do not become reasonable or unreasonable by the execution of variations.
The extent to which bill of quantities (BoQ) rates are applicable for valuing variations in the works, is a common cause of conflict on projects, particularly when there are substantial changes in quantities. This can be a particular issue if the rate in question is abnormally high or low due to the fact that an error has been incurred. Contractors argue that abnormally low rates compound losses, while clients point out that abnormally high rates exaggerate contractor profits.
In the case of Henry Boot Construction Ltd. v Alstom Combined Cycles, Henry Boot Construction Ltd. was employed by Alstom to undertake civil engineering works at a power station. Boot quoted a price for temporary sheet piling and this figure was included in the contract. As the works proceeded however, variation instructions affecting the sheet piling were issued.
Boot’s price was found to have been calculated incorrectly, meaning that the additional quantity required by the variation would have given them a large profit. Boot argued that the contract rates must be adhered to whereas Alstom argued that a fair valuation should be made.
At the trial, the judge emphasised the importance of the contract rates, ruling that they were ‘sacrosanct, immutable, and not subject to correction’ on the basis of one party’s dissatisfaction with them. He referred to Clause 55(2) in the relevant ICE Standard Form (6th ed.) contract which stipulated that there should be no rectification of errors, omissions or estimates, and that a mistake in a rate or price bound both parties equally.
The Court of Appeal endorsed the judge’s ruling in 2000, confirming that pricing errors do not allow the parties to adjust the rates.
The rates may however be adjusted where they are used to value variations:
- Where the works are not executed under similar conditions.
- Where the rate is rendered inapplicable by a substantial change in the quantities.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.