Payment for extra work
Building works are complex, and it is common for a contractor to carry out works not described in the original contract documents for which they consider they are entitled to additional payment over and above the original contract sum. However, the fact that a contractor has carried out extra work does not automatically mean they have a right to payment for it.
The exact conditions under which additional payment is merited should be set out in the terms of the contract, however, generally, the contractor must be able to prove the following:
- The contract sum does not include the additional work.
- There was an express or implied promise to compensate the contractor for the work.
- The work was instructed by an authorised agent.
- Any conditions precedent to payment, as imposed by the contract, have been fulfilled.
For example, where the contractor has carried out extra work or uses superior materials to those specified, but they have not been instructed to do so, this will not entitle them to extra payment. Similarly, if the employer agrees to different work, they will not necessarily be liable for any additional payment if they were not informed of the increased costs involved.
Generally, in an emergency situation where a contractor pays a sum to preserve the employer’s property, and has not been possible to obtain instructions from the employer, the contractor will be entitled to additional payment.
If the employer refuses to provide additional payment for extra work, the contractor may refuse to carry out the work. If the employer promises the additional payment, and it later transpires that the work is included in the original contract sum and so is not ‘extra’, the promise to pay will generally not be binding.
Even if the employer has had the benefit of extra work, in the absence of written instructions, it is generally held that the contractor will be unable to recover payment.
The contractor should consider whether what they think is ‘extra work’ is provided for by the clauses of the contract.
Typically, contracts provide for changes to the works described in the contract documents through variation clauses. A variation (sometimes referred to as a variation instruction, variation order or change order) is an alteration to the scope of works in the form of an addition, substitution or omission from the original scope of works. Variations may also be deemed to occur if the contract documents do not properly describe the works actually required.
Variation instructions must be clear as to what is and is not included, and may propose the method of valuation.
For more information see: Variations.
[edit] Related articles on Designing Buildings
Featured articles and news
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.





















