Estimate
The term ‘estimate’ is a very broad one that refers to any activity that attempts to quantify something. In the construction industry, it is typically used in relation to the approximate costs associated with a construction project, used, for example to assess the viability or affordability of the project or aspects of it.
An estimate is an attempt to predict the likely expenditures associated with a project as accurately as possible. The degree of detail and the accuracy of estimates will typically increase as the project progresses, more decisions have been made, and more information is available, however, their true accuracy only becomes apparent once the project is complete and the actual costs incurred.
At the outset, estimates may be made to help determine whether a project is affordable and to set a budget. They will then be used to test design options to ensure they are in line with the budget.
A pre-tender estimate (PTE) is a final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers.
Contractors, subcontractors and suppliers will then prepare definitive cost estimates to submit tenders in the construction bidding process to compete for the award of contracts.
There are a number of methods available for estimating, depending on the stage of the project and the information available:
- Benchmarking, which is a process by which other similar projects are used as comparisons.
- Breaking down an overall estimated construction cost into percentages for different elements, based on the experience of the cost consultant.
- Measuring defined quantities from drawings.
For more information see: Types of estimating.
Initial cost estimates might include wider project costs that the client might incur, such as; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on. Later in the project, estimates are likely to focus on the construction cost of the project. It is important to be clear therefore what costs are being included in estimates, and estimates might be accompanied by a schedule of the assumptions that have been made.
Estimates will generally include contingencies, which are downside risk estimates that make allowance for unknown risks associated with a project. At the preliminary business plan stage, estimates might include a 15% contingency, but this may then be reduced as the project progresses and risks pass.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines estimate as: A prediction or forecast of the resources (i.e. time, cost, materials, etc.) required to achieve or obtain an agreed scope of work (i.e. for an investment, activity, project, etc.).’
[edit] Related articles on Designing Buildings
- Analogous estimating.
- Base cost estimate.
- Benchmarking.
- Bottom-up estimation.
- Budget.
- Building works estimate.
- Cash flow projection.
- Common mistakes in bill of quantities.
- Contingencies.
- Cost overruns.
- Cost plans.
- Elemental estimating.
- Elemental method.
- Estimator.
- Expert opinion estimating.
- Extra over (EO).
- Initial cost appraisal.
- Irrelevant cost.
- Operational rate estimate?.
- Order of cost estimating.
- Parametric estimating.
- Post tender estimate.
- Pre-tender estimate.
- Spon's Price Book.
- Tender pricing document.
- Three point estimation.
- Top down estimating.
- Types of estimating.
- Unit rate estimating.
Featured articles and news
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.