Initial cost appraisal for design and construction
Initial cost appraisals are carried out without the benefit of a design for the project. They include client costs that may not feature in later cost plans and as a result will almost certainly need input from the client's finance director or financial advisers.
Once the initial cost appraisal is completed, the client will decide the scope of costs that will in future be monitored by the cost consultant and those that will be monitored and controlled by the client organisation.
Initial cost appraisals break down the overall project budget based on information provided by the client, an analysis of comparable projects and the experience of the cost consultant.
Initial cost appraisals might include:
- Assumptions about the nature of the project, identifying variables. This will include a guestimate of gross internal floor area and a rate psm to be applied from a range of historical data. Repetition with standard solutions carries with it cost efficient options. For more information, see Cost of building.
- Inclusions and exclusions.
- Look at location and site constraints. Central London will attract a premium. Ground conditions and proximity of neighbouring buildings affect costs.
- Adjust for market conditions.
- The building's function and facilities influence design loadings, floor to floor heights and structural spans which may affect costs. Special spaces with acoustic or vibration control will attract a premium.
- State the procurement route as an assumption.
- Land costs and purchase prices.
- Book value.
- Legal fees (including vendor).
- Agent fees (including vendor).
- Stamp duty.
- Site investigations and surveys.
- Demolition.
- Consultant team fees including expenses and unusual items such as models.
- Running costs.
- Building and infrastructure costs. At this stage building and infrastructure costs should be set on an overall unit basis, based on comparable projects, with assumptions relating to different types of areas and abnormal items. Units costs could include the number of; dwelling units, parking spaces, rentable area, hotel bedrooms, hospital beds, prison cells, and so on.
- Fixtures, fittings and equipment.
- Relocation / migration costs.
- Promotion and marketing.
- Capital gains tax.
- Corporation tax.
- Irrevocable VAT.
- Planning fees.
- Building control fees.
- Void costs.
- Insurance.
- Establishment costs.
- Funding costs.
- Capital allowances.
- Grants.
- Inflation escalation.
- Operational and whole-life cycle costs.
- Allocation of contingencies sum.
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bid strategies.
- Bills of quantities.
- Budget.
- Business plan.
- Common arrangement of work sections.
- Contract sum.
- Contract sum analysis.
- Cost-benefit analysis in construction.
- Cost consultant.
- Cost information.
- Cost overruns.
- Cost plans.
- Elemental cost plan.
- Estimate.
- Final account.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender pricing document.
- Whole-life costs.
Featured articles and news
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.