New Rules of Measurement
For a comparison of the Standard Method of Measurement and the New Rules of Measurement see: Comparison of SMM7 with NRM2.
[edit] Introduction
The New Rules of Measurement (NRM) are published by the Royal Institution of Chartered Surveyors' (RICS) Quantity Surveying and Construction Professional Group. They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects. Adopting a standard methodology such as NRM facilitates consistency and benchmarking and helps avoid disputes.
NRM is a suite of documents, comprising three volumes; NRM1, NRM2 and NRM3.
[edit] NRM1: Order of cost estimating and cost planning for capital building works.
NRM 1 was first published in February 2009 (as NRM Order of cost estimating and elemental cost planning). Now in its second edition, it provides guidance on the quantification of building works in order to prepare order of cost estimates and cost plans, as well as approximate estimates. It also includes guidance about quantifying wider costs such as preliminaries, overheads and profit, risk allowances, and inflation.
The second edition has been renamed to better distinguish between capital building works and building maintenance works, and the arrangement of elements has been revised. It became operative on 1 January 2013.
See NRM1 for more information.
[edit] NRM2: Detailed measurement for building works.
NRM2 was published in April 2012. It became operative on 1 January 2013 and replaced the Standard Method of Measurement, seventh edition (SMM7) on 1 July 2013.
NRM2 establishes detailed measurement rules allowing the preparation of bills of quantities, quantified schedules of works and schedules of rates in order to obtain tender prices. Guidance is also provided on the content, structure and format of bills of quantities.
See NRM2 for more information.
[edit] NRM3 - Order of cost estimating and cost planning for building maintenance works.
NRM3 was published in March 2014. It allows the quantification and description of maintenance works. It can be used for initial order of cost estimates, general cost plans and asset-specific cost plans. It also provides guidance on procurement and cost control.
NRM3 also offers guidance about the measurement of other items associated with maintenance works that are not included in work items.
See NRM3 for more information.
[edit] Reasons for the changes
It is suggested by the RICS that together, the new suite of documents will better reflect the way the industry works, for example:
- Better meeting the needs of clients.
- Providing for more up-front detail.
- Allowing better consideration of the full costs of a construction project (for example, marketing costs, fees and charges, the cost of acquiring land, planning costs, relocation costs, the cost of finance and so on).
- Providing a better method for quantifying risk.
The RICS also suggest that it will facilitate “...greater cross-industry working, the introduction of Building Information Modelling and effectively analysing the costs of construction projects” ref RICS.
As well as a set of rules for how to quantify building work, NRM is intended to provide a toolkit for cost management that will be central to controlling costs as a project develops. It provides guidance on how measurement changes as design progresses, how cost centres can be included in a single project cost plan, how to assess the cost of risk, how to assess fees, what information is required to make key decisions and so on.
The new NRM volumes were published alongside guidance on conflict avoidance and dispute resolution and retention. These will form part of the RICS QS and construction standards (the Black Book).
Notes:
- Contracts that refer to SMM7 will have to be revised when it is superceded by NRM. Many of the publishing bodies are now preparing amendments (for example JCT).
- NRM has moved away from the Common Arrangement of Work Sections (CAWS) to adopt its own system of indexing.
- For a detailed comparison of NRM2 with SMM7, see Comparison of SMM7 with NRM2.
- The New Rules of Measurement are accompanied by the 'Black Book', the QS and construction standards. Together they provide a suite of tools to help the construction industry work more collaboratively and consistently.
[edit] Related articles on Designing Buildings
- All-in rates.
- Approximate quantities.
- BCIS.
- BCIS elements.
- Bill of quantities.
- Black book.
- Building People.
- Classification, an introduction.
- Code of measuring practice.
- Common Arrangement of Work Sections (CAWS).
- Comparison of SMM7 with NRM2.
- Conversion of material volumes.
- Cost plans.
- Elemental cost plan.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Order of cost estimate.
- RICS.
- RICS Property Measurement.
- RICS publishes Land Measurement for Planning and Development Purposes.
- Schedule of work.
- Spon's Price Book.
- Standard Method of Measurement (SMM7).
- Surveyor.
- Tender.
- Tender documentation.
- Uniclass.
[edit] External references
- RICS: RICS has released new guidance for quantity surveyors and other members working in the construction sector.
- RICS: NRM 1 and NRM 2 are available.
- nbs video: The New Rules of Measurement.
- RICS QS and construction standards (the Black Book).
- nbs: Coordinating Common Arrangment, Uniclass, NBS and Rules of Measurement.
Featured articles and news
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Comments
the 3 volumes of NRM were updated in Dec 2021.