Common Arrangement of Work Sections
The Common Arrangement of Work Sections (CAWS) was developed by the Construction Project Information Committee (CPIC), a pan-industry organisation with representatives from key industry institutes.
It was developed as a result of research demonstrating that the quality of construction information was a very significant determinant of the quality of construction. It was recognised that standardisation of the way production information was created and classified could help improve quality, and that the commonly used CISfb classification was not sufficiently comprehensive to achieve this.
CAWS established a consistent arrangement for specifications and bills of quantities. It was first published in 1987 and was updated by CPIC in 1998 to align it with the Unified Classification for the Construction Industry (Uniclass). In 2005 nbs submitted to CPIC, modifications to the services sections of CAWS for consideration and following 5 years of consultation these changes were accepted.
CAWS is the categorisation of work that is used for the National Building Specification (NBS – which before 1987 followed the CISfB structure), National Engineering Specification (NES), the Standard Method of Measurement, currently in its 7th Edition (SMM7) and a number of industry pricing books such as Spons, Laxtons and Wessex.
CAWS has since been incorporated into Table J of Uniclass, which was also developed by CPIC. Uniclass is a classification system for organising library materials, product literature and project information.
In 2011, the CPIC used the nbs proposals for re-classification of the work sections in CAWS and Uniclass Table J as the basis of a consultation process for revising Uniclass. This development of Uniclass as a whole is considered to better accommodate civil engineering and process engineering alongside architecture and landscape, it also better enables the description of systems in performance terms, and is more suited to accommodating facilities management.
The main categories are:
- A - Preliminaries
- B - Complete buildings / structures / units
- C - Demolition / Alteration /Renovation
- D - Groundwork
- E - In situ concrete / Large precast concrete
- F - Masonry
- G - Structural / Carcassing metal / timber
- H - Cladding / Covering
- J - Waterproofing
- K - Linings / Sheathing / Dry partitioning
- L - Windows / Doors / Stairs
- M - Surface finishes
- N - Furniture / Equipment
- P - Building fabric sundries
- Q - Paving / Planting / Fencing / Site furniture
- R - Disposal Systems
- S - Piped supply systems
- T - Mechanical heating / Cooling / Refrigeration systems
- U - Ventilation / Air conditioning systems
- V - Electrical supply / power / lighting systems
- W - Communications / Security / Control systems
- X - Transport systems
- Y - General Engineering Services
- Z - Building fabric reference specification
Each section includes further sub-classification and offers detailed information and supplementary rules. For more information see: Common arrangement of work sections classification.
NB: SMM7 has been replaced by the New Rules of Measurement (NRM) which has moved away from CAWS, to adopt its own system of indexing. See New Rules of Measurement for more information.
[edit] Related articles on Designing Buildings
- Bills of quantities.
- BIM classification.
- CI/SfB.
- Classification, an introduction.
- Common arrangement of work sections classification.
- Comparison of SMM7 with NRM2.
- Construction Project Information Committee.
- Elemental cost plan.
- How to take off construction works.
- New Rules of Measurement.
- Preliminaries.
- Production information.
- Specifications.
- Spot items.
- Standard Method of Measurement (SMM7).
- Sundry items.
- Uniclass.
- Work section.
[edit] External references
- CPIC.
- NBS.
- NBS article on CAWS reclassification.
- NBS article on Co-ordinating CAWS and NRM.
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.