Remeasurement
Civil Engineering Procedure 7th Edition, published by the Institution of Civil Engineers in 2016, suggests that remeasurement (or occasionally re-measurement) is the:
…calculation of the actual quantities of work ordered on the contractors in order to certify the payment due to a contractor. Remeasurement is also known as measure-and-value’. |
There is a subtle difference between the term remeasurement and the term admeasurement, in that remeasurement refers to the entire process of measuring again the quantities of work undertaken, whereas admeasurement refers only to the difference between the estimated quantity and the actual quantity.
Remeasurement contracts, measurement contracts or measure and value contracts may be necessary on projects where the type of works required can be described in reasonable detail when they are tendered, but the amount cannot. For example, excavation works where the quantity of excavation required is difficult to assess until after the works have begun.
Instead of giving a firm price, rates are provided in the contractor’s tender, either as part of the priced approximate bill of quantities, or within a schedule of rates. Then the actual quantities of work carried out are measured and the tendered rates applied to those quantities. The contractor is paid for the actual work they have done. As a result, the quantities paid for may vary from the original estimates.
See Measurement contract for more information.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Admeasurement.
- Bills of quantities.
- Construction contract.
- Contract sum.
- Cost reimbursable contract.
- Difference between lump sum and measurement contracts.
- Emerging cost contract.
- Force account work.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Measurement contract.
- Measured term contract.
- Procurement route.
- Quantum meruit.
- Schedule of rates
- Schedule of rates term contract.
- Tender.
- Unit rates basis of payment.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..