The difference between a prime cost sum and a provisional sum
Contents |
[edit] Introduction
There is sometimes confusion regarding two items that may appear in standard forms of building contract – prime cost sums (PC or PC sums) and provisional sums (PS). They both relate to allowances made for certain costs in the absence of exact figures, but they are actually quite different.
[edit] What is a prime cost sum?
A prime cost sum is an allowance, usually calculated by the cost consultant, for the supply of work or materials to be provided by a sub-contractor or supplier that will be nominated by the client - that is, a sub-contractor or supplier that is selected by the client to carry out an element of the works and imposed on the main contractor. The main contractor is entitled to add mark up and attendance costs to the allowance.
Actual payments are made based on the quotations/invoices of the supplied items plus the addition of reasonable/agreed percentages for overhead costs and profits.
If the main contractor's actual costs then turn out to be higher, the contract sum is increased, and if the main contractor's actual costs are lower, the contract sum is reduced.
For more information see: Prime cost sum.
[edit] What is a provisional sum?
A provisional sum is an allowance, usually estimated by a cost consultant, for a specific element of the works that has not been defined in enough detail at the time that prices are sought from tenderers, for those tenderers to accurately price them. Provisional sums are replaced by valuations of the work actually done as the project progresses and so the contract sum may increase or decrease.
Depending on the degree to which the works that the provisional sum relates to can be described at the tender stage, provisional sums may be referred to as 'defined' or 'undefined'.
- Defined provisional sums are those which have been described in sufficient detail for the tenderer to make allowance for them in their programming, planning and pricing preliminaries.
- Undefined provisional sums are less well described and so the tenderer cannot be expected to make allowance for them in their programming, planning and pricing preliminaries.
For more information see: Provisional sum.
[edit] Summary
In summary, both provisional sums and prime cost sums are allowances for items that cannot be accurately priced when tenders are sought. Provisional sums relate to items for which there is insufficient information - such as earthworks for example, where it may be difficult to determine what is required before some excavation has been undertaken, whereas prime cost sums relate to suppliers or sub-contractors that are nominated by the client, such as specialist equipment suppliers for example.
As both add a degree of uncertainty to the contract sum, they should generally be discouraged.
[edit] Related articles on Designing Buildings
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Is PC for a specific element? It seems that it does not match the Home Building Contract?
It is for a specific element of the works. This is a term used in the UK, it may be that definitions / contract terms are different in other countries.
That's so vague
As with all construction terms, the exact definition will depend on the contract that is being used.