The difference between a prime cost sum and a provisional sum
Contents |
[edit] Introduction
There is sometimes confusion regarding two items that may appear in standard forms of building contract – prime cost sums (PC or PC sums) and provisional sums (PS). They both relate to allowances made for certain costs in the absence of exact figures, but they are actually quite different.
[edit] What is a prime cost sum?
A prime cost sum is an allowance, usually calculated by the cost consultant, for the supply of work or materials to be provided by a sub-contractor or supplier that will be nominated by the client - that is, a sub-contractor or supplier that is selected by the client to carry out an element of the works and imposed on the main contractor. The main contractor is entitled to add mark up and attendance costs to the allowance.
Actual payments are made based on the quotations/invoices of the supplied items plus the addition of reasonable/agreed percentages for overhead costs and profits.
If the main contractor's actual costs then turn out to be higher, the contract sum is increased, and if the main contractor's actual costs are lower, the contract sum is reduced.
For more information see: Prime cost sum.
[edit] What is a provisional sum?
A provisional sum is an allowance, usually estimated by a cost consultant, for a specific element of the works that has not been defined in enough detail at the time that prices are sought from tenderers, for those tenderers to accurately price them. Provisional sums are replaced by valuations of the work actually done as the project progresses and so the contract sum may increase or decrease.
Depending on the degree to which the works that the provisional sum relates to can be described at the tender stage, provisional sums may be referred to as 'defined' or 'undefined'.
- Defined provisional sums are those which have been described in sufficient detail for the tenderer to make allowance for them in their programming, planning and pricing preliminaries.
- Undefined provisional sums are less well described and so the tenderer cannot be expected to make allowance for them in their programming, planning and pricing preliminaries.
For more information see: Provisional sum.
[edit] Summary
In summary, both provisional sums and prime cost sums are allowances for items that cannot be accurately priced when tenders are sought. Provisional sums relate to items for which there is insufficient information - such as earthworks for example, where it may be difficult to determine what is required before some excavation has been undertaken, whereas prime cost sums relate to suppliers or sub-contractors that are nominated by the client, such as specialist equipment suppliers for example.
As both add a degree of uncertainty to the contract sum, they should generally be discouraged.
[edit] Related articles on Designing Buildings
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Is PC for a specific element? It seems that it does not match the Home Building Contract?
It is for a specific element of the works. This is a term used in the UK, it may be that definitions / contract terms are different in other countries.
That's so vague
As with all construction terms, the exact definition will depend on the contract that is being used.