Final certificate for construction contracts
Contents |
[edit] Introduction
The final certificate is certification by the contract administrator that a construction contract has been fully completed. It is issued at the end of the defects liability period and has the effect of releasing all remaining money due to the contractor, including any remaining retention.
The value of the final certificate will be based on the final account agreed by the cost consultant and the contractor. This means that all patent defects must have been remedied, all adjustments to the contract sum must have been agreed and all claims settled.
Where proceedings have been commenced in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings. In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other proceedings may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice - see Housing Grants, Construction and Regeneration Act for more information).
[edit] Alternative procedures
In design and build contracts (such as Joint Contracts Tribunal (JCT) DB 16) the final certificate may be described as the final statement.
In construction management contracts, where there are a number of trade contracts, final statements are issued for each trade contract. Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the whole project.
There is a similar procedure on management contracts, where final certificates are issued by the management contractor for each individual works contract, and then once all works contracts have received a final certificate, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts) and a final certificate is issued to the management contractor.
[edit] Alternative meaning
Rather confusingly, the term 'final certificate' can also refer to a completion certificate issued by a building control body in relation to the building regulations.
Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Final certificate refers to the certificate issued by the approved inspector to the person carrying out the work and the local authority and confirms that the work in the initial notice is complete and that the approved inspector is satisfied that it complies with the relevant requirements of the Building Regulations.’
See Building regulations completion certificate for more information.
[edit] Related articles on Designing Buildings Wiki
- Building regulations completion certificate.
- Certificates in the construction industry.
- Contract administrator.
- Defects liability period.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- Retention.
- Interim certificates.
- Sectional completion.
- Topping out.
- What is a final account.
- Work-to-complete list.
Featured articles and news
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Comments
What does a 'Part Final Certificate' mean? Does it mean for the specified works it is fully complete (but there are other works as part of the application) Or that the specified works are part complete?
This might relate to a final certificate for part of the works - ie where there is partial possession or sectional completion - see the comments at the end of those articles.
However, the specific term 'part final certificate' is more commonly used in relation to building regulations approvals.