Final certificate for construction contracts
Contents |
[edit] Introduction
The final certificate is certification by the contract administrator that a construction contract has been fully completed. It is issued at the end of the defects liability period and has the effect of releasing all remaining money due to the contractor, including any remaining retention.
The value of the final certificate will be based on the final account agreed by the cost consultant and the contractor. This means that all patent defects must have been remedied, all adjustments to the contract sum must have been agreed and all claims settled.
Where proceedings have been commenced in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings. In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other proceedings may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice - see Housing Grants, Construction and Regeneration Act for more information).
[edit] Alternative procedures
In design and build contracts (such as Joint Contracts Tribunal (JCT) DB 16) the final certificate may be described as the final statement.
In construction management contracts, where there are a number of trade contracts, final statements are issued for each trade contract. Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the whole project.
There is a similar procedure on management contracts, where final certificates are issued by the management contractor for each individual works contract, and then once all works contracts have received a final certificate, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts) and a final certificate is issued to the management contractor.
[edit] Alternative meaning
Rather confusingly, the term 'final certificate' can also refer to a completion certificate issued by a building control body in relation to the building regulations.
Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Final certificate refers to the certificate issued by the approved inspector to the person carrying out the work and the local authority and confirms that the work in the initial notice is complete and that the approved inspector is satisfied that it complies with the relevant requirements of the Building Regulations.’
See Building regulations completion certificate for more information.
[edit] Related articles on Designing Buildings Wiki
- Building regulations completion certificate.
- Certificates in the construction industry.
- Contract administrator.
- Defects liability period.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- Retention.
- Interim certificates.
- Sectional completion.
- Topping out.
- What is a final account.
- Work-to-complete list.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.


























Comments
What does a 'Part Final Certificate' mean? Does it mean for the specified works it is fully complete (but there are other works as part of the application) Or that the specified works are part complete?
This might relate to a final certificate for part of the works - ie where there is partial possession or sectional completion - see the comments at the end of those articles.
However, the specific term 'part final certificate' is more commonly used in relation to building regulations approvals.