Prime cost in construction contracts
In general terms, the ‘prime cost’ is the sum of the direct cost of materials and labour associated with a production process. It is the direct cost of the inputs to a process that are necessary to create the output. If the prime cost can be lowered, the process may become more profitable.
In construction, the term ‘prime cost sum’ (PC sum) is an allowance for the supply of labour, plant and materials to be provided by a contractor or supplier that will be nominated by the client. The allowance is exclusive of any profit mark up or attendance (such as material handling, scaffolding and rubbish clearance etc) by the main contractor. See prime cost sum for more information.
Prime cost contracts (sometimes referred to as cost plus contracts or cost reimbursement contracts) are contracts in which the contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for profit and overheads.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete, for example for urgent alteration or repair work. See Prime cost contract for more information.
Adjustments may be permitted to prime costs during the period of a contract to allow for inflation (fluctuations).
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.


















Comments
Construction on this page has been spelt incorrectly! - well spotted, this has been fixed