Prime cost in construction contracts
In general terms, the ‘prime cost’ is the sum of the direct cost of materials and labour associated with a production process. It is the direct cost of the inputs to a process that are necessary to create the output. If the prime cost can be lowered, the process may become more profitable.
In construction, the term ‘prime cost sum’ (PC sum) is an allowance for the supply of labour, plant and materials to be provided by a contractor or supplier that will be nominated by the client. The allowance is exclusive of any profit mark up or attendance (such as material handling, scaffolding and rubbish clearance etc) by the main contractor. See prime cost sum for more information.
Prime cost contracts (sometimes referred to as cost plus contracts or cost reimbursement contracts) are contracts in which the contractor is paid the prime cost (the actual cost of labour, plant and materials) and a fee for profit and overheads.
Prime cost contracts are used where an early or immediate start on site is required even though design information is not complete, for example for urgent alteration or repair work. See Prime cost contract for more information.
Adjustments may be permitted to prime costs during the period of a contract to allow for inflation (fluctuations).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments
Construction on this page has been spelt incorrectly! - well spotted, this has been fixed