Attendance for construction
Attendance is the main contractor’s mark up for specific services it has to provide for individual suppliers or sub-contractors. This might include items such as material handling, scaffolding and rubbish clearance.
Attendance can be ‘general’ or ‘special’.
General attendance is the description of main contractor attendance available site wide to all suppliers or sub-contractors such as:
- Welfare facilities.
- External scaffolding.
- Temporary power and lighting.
- Platform and passenger hoists.
- Tower crane lifts by prior arrangement.
- Site security.
- Waste disposal.
Special attendance is specific to a particular supplier or sub-contractor if it requests that it is provided by the main contractor, such as:
- Special hoists.
- Builders work such as a concrete plinth.
- Special scaffolding.
It is important to establish within the contract documents whether items that suppliers or sub-contractors require will constitute attendances that will be provided by the main contractor, or whether they will provide them themselves (such as their own specialist equipment).
Attendance should not be confused with general site preliminaries or builder’s work in connection with mechanical and electrical services. These items are separately priced.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.
Undervaluing our industrial past
Heritage value changes as taste for building styles changes.
Changing expectations around competence and compliance
New information sheet from CIAT.
Grenfell investigation files passed to CPS
Angela Rayner apologises on behalf of the British state.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.