Building regulations completion certificate
|
Contents |
[edit] What are the building regulations?
The building regulations apply to most new buildings and many alterations to existing buildings. They set out:
- What qualifies as ‘building work’ and so fall under the control of the regulations.
- What types of buildings are exempt (such as temporary buildings).
- The notification procedures that must be followed when starting, carrying out, and completing building work.
- Requirements for specific aspects of building design and construction.
[edit] How are building regulations approvals sought?
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out. On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
Building Regulations approvals can be sought either from the building control department of the local authority or from an approved inspector. These are referred to as the building control body.
A series of notifications must be given to the building control body at key stages of the works so that appropriate inspections can be carried out.
[edit] What is a building regulations completion certificate?
Notice must be given to the building control body when the works are completed.
A completion certificate is then issued by the building control body (or a 'final certificate' if the building control body is an approved inspector - although this can be confusing as the term final certificate is also used in construction contracts to refer to completion of the works), providing formal evidence that the building works have been approved and that, in so far as it is reasonable to determine, the works have been carried out in accordance with the building regulations.
Completion certificates were introduced for building regulations applications in the late-1980s and 1990s. However, solicitors generally did not consider building regulations approvals in property searches during conveyancing, particularly if alterations were more than 12 months old. In the case of Cottingham v Attey Bower & Jones [2000], this practice was judged to be negligent. Subsequently, it has become very important for owners to obtain a completion certificate for works they have undertaken, or there may be difficulties in selling a property.
Completion certificates became a requirement where buildings were within the scope of the Regulatory Reform (Fire Safety) Order 2005 (that is, for non-domestic buildings and blocks of flats). For other properties, completion certificates were only issued if they were requested.
However, in December 2012, The Building Regulations &c. (Amendment) Regulations 2012 were introduced. This amendment removed the need to request a completion certificate from a local authority and instead required that where a local authority is satisfied that works meet the building regulations, it must give a completion certificate. It also requires that completion certificates are issued within 8 weeks. (Ref. Communities and Local Government Circular 02/2012 19 December 2012)
No such requirement was introduced for building notice applications, although completion certificates may still be requested from the local authority.
If a certificate has been lost, a copy can be obtained from the local authority, although a fee may be payable.
Where minor works are carried out to a property, a certificate may be issued by a trades person under the competent persons schemes. This allows registered installers who are competent in their field to self-certify certain types of building work. For example, air-tightness testing, plumbing and heating installers, electrical installers, cavity wall insulation installers, and so on. These are referred to as building regulations certificates of compliance.
See also: Plans certificate.
NB Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Completion certificates are issued by the local authority to confirm that it has taken reasonable steps to ensure that there is evidence, but not necessarily conclusive evidence, that the work complies with the relevant requirements of the Building Regulations.’
Note, While Building control bodies will now issue certificates confirming that works undertaken comply with the building regulations, it is not always clear whether the building control body keeps a record of precisely what those works were, particularly if the approval process was by a building notice rather than full plans application. It may be difficult therefore for a building control body to be certain whether works that have been undertaken were part of the approved works, or whether they have been carried out subsequently.
[edit] Related articles on Designing Buildings
- Approved documents.
- Approved inspector.
- Building control body.
- Building notice.
- Building Regulations Compliance Statement.
- Building regulations inspection.
- Certificates in the construction industry.
- Competent persons schemes.
- Local authority.
- Northern Ireland building regulations.
- Plans certificate.
- Scottish building standards.
- The Building Act.
- Welsh building regulations.
- What approvals are needed before construction begins.
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Can a Building Regs Completion Certificate be issued in respect of a Section of works which will receive a sectional completion certificate under a building contract or would such a certificate be a 'partial certificate' and therefore not have the same effect as a Building Regs Completion Certificate?
Check with the building control body - but it seems likely that it would only approve the entirety of the works to which the application relates unless a staged approval was agreed in advance and was therefore part of the fee calculation.