Building regulations completion certificate
![]() |
Contents |
[edit] What are the building regulations?
The building regulations apply to most new buildings and many alterations to existing buildings. They set out:
- What qualifies as ‘building work’ and so fall under the control of the regulations.
- What types of buildings are exempt (such as temporary buildings).
- The notification procedures that must be followed when starting, carrying out, and completing building work.
- Requirements for specific aspects of building design and construction.
[edit] How are building regulations approvals sought?
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out. On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
Building Regulations approvals can be sought either from the building control department of the local authority or from an approved inspector. These are referred to as the building control body.
A series of notifications must be given to the building control body at key stages of the works so that appropriate inspections can be carried out.
[edit] What is a building regulations completion certificate?
Notice must be given to the building control body when the works are completed.
A completion certificate is then issued by the building control body (or a 'final certificate' if the building control body is an approved inspector - although this can be confusing as the term final certificate is also used in construction contracts to refer to completion of the works), providing formal evidence that the building works have been approved and that, in so far as it is reasonable to determine, the works have been carried out in accordance with the building regulations.
Completion certificates were introduced for building regulations applications in the late-1980s and 1990s. However, solicitors generally did not consider building regulations approvals in property searches during conveyancing, particularly if alterations were more than 12 months old. In the case of Cottingham v Attey Bower & Jones [2000], this practice was judged to be negligent. Subsequently, it has become very important for owners to obtain a completion certificate for works they have undertaken, or there may be difficulties in selling a property.
Completion certificates became a requirement where buildings were within the scope of the Regulatory Reform (Fire Safety) Order 2005 (that is, for non-domestic buildings and blocks of flats). For other properties, completion certificates were only issued if they were requested.
However, in December 2012, The Building Regulations &c. (Amendment) Regulations 2012 were introduced. This amendment removed the need to request a completion certificate from a local authority and instead required that where a local authority is satisfied that works meet the building regulations, it must give a completion certificate. It also requires that completion certificates are issued within 8 weeks. (Ref. Communities and Local Government Circular 02/2012 19 December 2012)
No such requirement was introduced for building notice applications, although completion certificates may still be requested from the local authority.
If a certificate has been lost, a copy can be obtained from the local authority, although a fee may be payable.
Where minor works are carried out to a property, a certificate may be issued by a trades person under the competent persons schemes. This allows registered installers who are competent in their field to self-certify certain types of building work. For example, air-tightness testing, plumbing and heating installers, electrical installers, cavity wall insulation installers, and so on. These are referred to as building regulations certificates of compliance.
See also: Plans certificate.
NB Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Completion certificates are issued by the local authority to confirm that it has taken reasonable steps to ensure that there is evidence, but not necessarily conclusive evidence, that the work complies with the relevant requirements of the Building Regulations.’
Note, While Building control bodies will now issue certificates confirming that works undertaken comply with the building regulations, it is not always clear whether the building control body keeps a record of precisely what those works were, particularly if the approval process was by a building notice rather than full plans application. It may be difficult therefore for a building control body to be certain whether works that have been undertaken were part of the approved works, or whether they have been carried out subsequently.
[edit] Related articles on Designing Buildings
- Approved documents.
- Approved inspector.
- Building control body.
- Building notice.
- Building Regulations Compliance Statement.
- Building regulations inspection.
- Certificates in the construction industry.
- Competent persons schemes.
- Local authority.
- Northern Ireland building regulations.
- Plans certificate.
- Scottish building standards.
- The Building Act.
- Welsh building regulations.
- What approvals are needed before construction begins.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Can a Building Regs Completion Certificate be issued in respect of a Section of works which will receive a sectional completion certificate under a building contract or would such a certificate be a 'partial certificate' and therefore not have the same effect as a Building Regs Completion Certificate?
Check with the building control body - but it seems likely that it would only approve the entirety of the works to which the application relates unless a staged approval was agreed in advance and was therefore part of the fee calculation.