Completion
Contents |
[edit] Introduction
The term ‘completion’ is often used in the context of buildings and construction projects, but there is no precise legal definition, and its meaning is dependent on the situation in which it is being used.
[edit] Property sales
In the context of property, completion is the point at which the price of the property is paid and transfer documents are dated, thereby completing the final step in the legal process of transferring the ownership of property.
[edit] Construction works
In relation to construction, the situation is considerably more complex as 'completion' is generally not a single event, but takes place in stages.
Most construction contracts will set a date by which the works described in the contract must be completed. However, this is not the date by which all obligations under the contract have to be discharged, but only the date by which 'practical completion' must be certified.
There is no absolute definition of practical completion, but very broadly, practical completion is deemed to have occurred when all the construction works that are described in the contract have been carried out, and the contract administrator issues a certificate of practical completion. For more information see: Practical completion.
This is followed by a defects liability period during which the contractor may be recalled to rectify defects which appear. At the end of the defects liability period, the contract administrator prepares a schedule of defects, listing those defects that have not yet been rectified, and agrees with the contractor the date by which they will be rectified. When the contract administrator considers all the items on the schedule of defects have been rectified, they issue a certificate of making good defects.
In effect, this marks the completion of the works. There may still be latent defects, which do not appear for some time, however, the building owner no longer has a contractual right to insist that the contractor rectifies any defects, and they must instead seek redress in an action for damages, for breach of contract, or for negligence. In the case of dwellings there is a statutory remedy provided by the Defective Premises Act 1972.
NB: Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others. See Sectional completion for more information.
Partial possession clauses may permit the client or tenants to take possession of part of a building or site, even if the works are ongoing or there are defects that have not been rectified. See Partial possession for more information.
[edit] Other commercial contracts
Under other commercial contracts (i.e. those that relate to goods and services), the contract performance is not considered 'complete' until the obligations imposed by the contract have been fulfilled.
See also: Failure to complete construction works.
[edit] Related articles on Designing Buildings
- Building completion.
- Certificate of non completion.
- Completion date.
- Difference between practical completion and partial possession.
- Early use.
- Failure to complete construction works.
- Handover to client.
- Partial possession.
- Practical completion.
- Sectional completion.
- Substantial completion.
- Topping out.
- Work-to-complete list.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.