Guaranteed maximum price for construction contracts
A guaranteed maximum price (GMP) is a form of agreement with a contractor in which it is agreed that the contract sum will not exceed a specified maximum.
Typically, this is a mechanism used on design and build contracts where the contractor has responsibility for completing the client’s design and for carrying out the construction works, so they are in a good position to control costs.
If the actual cost of the works is higher than the guaranteed maximum price, then the contractor must bear the additional cost. If the cost is lower than the guaranteed maximum price, then the contract should set out whether the savings made go to the client, to the contractor or are shared. This can create a ‘pain/gain’, or a target cost agreement, where the contractor is incentivised to make savings, but the client has the security of a cost cap.
Effectively, this sort of contract transfers risks for delivering the project from the client to the contractor. For example, if events such as exceptionally adverse weather or strikes occur, or if items that might otherwise have been the subject of provisional sums (such as complex groundworks, the nature of which cannot be determined until the ground is opened up), which on other forms of contract might have resulted in a claim by the contractor for loss and expense, on a guaranteed maximum price contract, the contractor has to bear any additional costs.
As a consequence the contractor is likely to tender a higher price. Effectively they price the risks that they are taking on. This may be acceptable to the client if their priority is certainty rather than the lowest possible cost, for example, if the client has fixed funding available that cannot be exceeded.
However, a guaranteed maximum price is not a panacea, and the price is not necessarily fixed. If the client requests ‘extras’, for example, if the scope of the works increases, then the contract must provide for the price to be increased. Similarly, if work is omitted, then the price should be reduced.
There is obviously scope here for disagreement about what constitutes a change that should result in a price adjustment, and there is the potential for the contractor to use the valuation of changes to recover costs they have incurred elsewhere. This can cause tension in a form of contract that was selected to provide certainty.
In deciding whether to seek a guaranteed maximum price, the client should assess the nature of the project, the likely risks and whether it is sensible to expect the contractor to bear those risks. If risks are priced by the contractor, but then do not transpire, the client will have paid for nothing, whilst if serious unforeseen problems are encountered, the contractor may attempt to find a way out of their obligation, or may be at risk of insolvency.
Whilst a simple project on a greenfield site might be suitable for a guaranteed maximum price, works to existing, older properties, or complex projects with inherent uncertainty (in particular in relation to ground works) might not. To assess these risks, it is important to ensure that proper investigations are undertaken and a fair apportionment of risks made. It is also important to ensure the client’s requirements have been clearly defined to avoid potential dispute about the nature of the works. A guaranteed maximum price is not an excuse to leap into the unknown and hope for the best.
Guaranteed maximum price contracts tend to be either bespoke (on small projects, often written by the contractor, and so potentially including hidden get-out clauses), or modified standard form contracts – which themselves have potential risks. It is important that these contracts have unambiguous wording, particularly where there are pain/gain provisions.
Despite the name ‘guaranteed maximum price’ the client should still ensure that they have an adequate contingency.
[edit] Related articles on Designing Buildings
- Construction contracts.
- Construction manager at-risk.
- Contingency.
- Contract sum.
- Design and build.
- Fixed price contract.
- Guaranteed maximum price with target cost.
- Force account work.
- Loss and expense.
- Lump sum contract - pros and cons.
- Modifying clauses in standard forms of contract.
- Price.
- Procurement route.
- Provisional sum.
- Relevant event.
- Target cost contract.
- Time and material contract (T&M).
Featured articles and news
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.



















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.