Time and material contract (T&M)
In the United States, a time and material contract (T&M) is a type of construction contract that commits the client to pay the contractor based upon the time spent on the works, the materials used, as well as a mark-up for profit. In the UK, this type of contract is known as a cost reimbursable contract or cost plus.
This differs from a fixed price contract which commits the client to pay the contractor a lump sum fee for fulfilling the contract regardless of the amount on labour, materials, and so on used. A T&M contract is typically used on projects where it is difficult to describe the extent of the works required accurately, or where specifications and requirements are likely to change as the project progresses.
The main items that can be included in a T&M contract are:
- Labour rates: The amount that will be charged for the workforce, which may also include insurance, taxes, and so on.
- Material mark-up: It is usual for the client to be charged the retail price for materials and for a mark-up to be added by the contractor if they have a pre-agreed wholesale price with the supplier.
- Not-to-exceed: A guaranteed maximum price which places an upper limit on what the client can be charged by the contractor.
The advantages of using a T&M contract include:
- It provides the client with cost transparency and allows them to verify invoices and timesheets to ensure the costs are correct.
- It allows for greater flexibility in the extent of the works required.
- It allows works to progress even when there is no definitive plan for how it will be completed.
- It saves time in the initial estimating process which otherwise has to be done to a much higher level of detail and accuracy.
- Although there is generally a limit on their profit, the contractor can proceed knowing they are going to recover expenses with some profit, and so they can avoiding cost-cutting.
The disadvantages of using a T&M contract include:
- It can prove more risky for the client to proceed without a clear understanding of the final cost.
- It can increase the likelihood of disputes arising.
- Errors or inaccurate estimates can leave them with a low profit that may not be deemed worthwhile.
- It can necessitate more involvement from the client to ensure the contractor is motivated to progressing the works on time and within budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.