Emerging cost contract
|
Emerging cost (Time and Materials (T&M)) contracts are most commonly used for rail infrastructure projects.
They are essentially cost reimbursable management contracts for a programme of works and services where the management contractor is paid direct costs identified in an 'estimate of project costs'. They provide for sophisticated management services along with sub-contracting the construction of the works.
However, while there may be target costs and schedules of rates for individual items of the programme of works, with associated incentives and penalties, there is no overall target cost. This means that the final value of the contract may not be known until the contract is complete. This can be useful where setting an overall target cost would restrict the client’s ability to vary the scope of works.
This means the client is accepting many of the financial risks of the project, and must have the expertise and appropriate controls to manage those risks.
Emerging cost contracts provide for value engineering and for the right to terminate if the cost estimate reaches an agreed percentage above the original estimate.
Emerging cost contracts are often applied over a defined period of time. The longer this period of time, the more consideration the contractor is likely to give to long-term performance issues in design and workmanship.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.