Emerging cost contract
|
Emerging cost (Time and Materials (T&M)) contracts are most commonly used for rail infrastructure projects.
They are essentially cost reimbursable management contracts for a programme of works and services where the management contractor is paid direct costs identified in an 'estimate of project costs'. They provide for sophisticated management services along with sub-contracting the construction of the works.
However, while there may be target costs and schedules of rates for individual items of the programme of works, with associated incentives and penalties, there is no overall target cost. This means that the final value of the contract may not be known until the contract is complete. This can be useful where setting an overall target cost would restrict the client’s ability to vary the scope of works.
This means the client is accepting many of the financial risks of the project, and must have the expertise and appropriate controls to manage those risks.
Emerging cost contracts provide for value engineering and for the right to terminate if the cost estimate reaches an agreed percentage above the original estimate.
Emerging cost contracts are often applied over a defined period of time. The longer this period of time, the more consideration the contractor is likely to give to long-term performance issues in design and workmanship.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.