Penalties in construction
In construction, the term 'penalty' typically refers to a financial payment imposed in the event of a breach of contract.
In 'Legione v Hateley' [1983], Mason and Deane JJ defined a penalty as follows:
“A penalty, as its name suggests, is in the nature of a punishment for non-observance of a contractual stipulation; it consists of the imposition of an additional or different liability upon breach of the contractual stipulation …”
However, 'penal' clauses, ie those that impose a punishment may not enforceable. Until recently, it was considered that they must be based on a genuine calculation of actual damages incurred. In effect therefore 'penalties' were not allowed, albeit the phrase was still commonly used to refer to the payment of damages or some other liability imposed upon breach of a contractual stipulation.
For example, liquidated and ascertained damages (LADs) are common in construction contracts, generally relating to the failure of the contractor to complete the construction works before the date required by the contract. However, they are generally based on a genuine calculation of damages, and if they are not, or if they are exorbitant, they may be considered a penalty by the courts and therefore may be unenforceable.
For more information see: Liquidated and ascertained damages.
This precedent was set by Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd, in which a contractual provision was considered to be a penalty if it was penal rather than a pre-estimate of loss. This determination is often made based on the terms and inherent circumstances of each particular contract, judged at the time of making the contract, not at the time of the breach.
However, in the case of 'Cavendish Square Holding BV v Talal El Makdessi (El Makdessi) and ParkingEye Ltd v Beavis' [2015], the Supreme Court re-considered the long-established principles underlying contractual penalty clauses. It held that the 'Dunlop rule' had been too rigidly applied, particularly where the inclusion of a penalty clause may have some clear justification, commercial or otherwise.
Lord Hodge stated that the "correct test for a penalty is whether the sum or remedy stipulated as a consequence of a breach of contract is exorbitant or unconscionable when regard is had to the innocent party's interest in the performance of the contract".
The new test set out by the Supreme Court recognises that the contractual party may have a legitimate interest which can be protected by a contractual penalty, and this interest need not be a genuine pre-estimate of loss. If that party is able to demonstrate that the penalty clause is being used to protect that legitimate interest, and it is not 'exorbitant or unconscionable', then they do not have to suffer a loss, and the predominant purpose of such a clause can be deter the other party from a certain breach of contract.
Examples of other penalties relevant to construction, not strictly related to breaches of contract, include:
- If landlords fail to carry out appropriate checks and rent a property to someone who is not allowed to stay in the UK, they could face a penalty of up to £3,000 per tenant.
- Local authorities can serve a legal notice on the person responsible for noise. If the noise problem persists they may be given a fixed penalty notice or taken to court and fined up to £5,000.
- Renting out a property that does not comply with the minimum energy efficiency standards might incur a penalty of up to £4,000 for domestic properties and up to £150,000 for non-domestic properties.
[edit] Related articles on Designing Buildings Wiki
- Compensation event.
- Contractual obligation.
- Damages in construction contracts.
- Delay damages.
- Liquidated damages in construction contracts.
- Liquidated v unliquidated damages.
- Measure of damages for construction contracts.
- Prompt payment code.
- Relevant event.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.