Guaranteed maximum price for construction contracts
A guaranteed maximum price (GMP) is a form of agreement with a contractor in which it is agreed that the contract sum will not exceed a specified maximum.
Typically, this is a mechanism used on design and build contracts where the contractor has responsibility for completing the client’s design and for carrying out the construction works, so they are in a good position to control costs.
If the actual cost of the works is higher than the guaranteed maximum price, then the contractor must bear the additional cost. If the cost is lower than the guaranteed maximum price, then the contract should set out whether the savings made go to the client, to the contractor or are shared. This can create a ‘pain/gain’, or a target cost agreement, where the contractor is incentivised to make savings, but the client has the security of a cost cap.
Effectively, this sort of contract transfers risks for delivering the project from the client to the contractor. For example, if events such as exceptionally adverse weather or strikes occur, or if items that might otherwise have been the subject of provisional sums (such as complex groundworks, the nature of which cannot be determined until the ground is opened up), which on other forms of contract might have resulted in a claim by the contractor for loss and expense, on a guaranteed maximum price contract, the contractor has to bear any additional costs.
As a consequence the contractor is likely to tender a higher price. Effectively they price the risks that they are taking on. This may be acceptable to the client if their priority is certainty rather than the lowest possible cost, for example, if the client has fixed funding available that cannot be exceeded.
However, a guaranteed maximum price is not a panacea, and the price is not necessarily fixed. If the client requests ‘extras’, for example, if the scope of the works increases, then the contract must provide for the price to be increased. Similarly, if work is omitted, then the price should be reduced.
There is obviously scope here for disagreement about what constitutes a change that should result in a price adjustment, and there is the potential for the contractor to use the valuation of changes to recover costs they have incurred elsewhere. This can cause tension in a form of contract that was selected to provide certainty.
In deciding whether to seek a guaranteed maximum price, the client should assess the nature of the project, the likely risks and whether it is sensible to expect the contractor to bear those risks. If risks are priced by the contractor, but then do not transpire, the client will have paid for nothing, whilst if serious unforeseen problems are encountered, the contractor may attempt to find a way out of their obligation, or may be at risk of insolvency.
Whilst a simple project on a greenfield site might be suitable for a guaranteed maximum price, works to existing, older properties, or complex projects with inherent uncertainty (in particular in relation to ground works) might not. To assess these risks, it is important to ensure that proper investigations are undertaken and a fair apportionment of risks made. It is also important to ensure the client’s requirements have been clearly defined to avoid potential dispute about the nature of the works. A guaranteed maximum price is not an excuse to leap into the unknown and hope for the best.
Guaranteed maximum price contracts tend to be either bespoke (on small projects, often written by the contractor, and so potentially including hidden get-out clauses), or modified standard form contracts – which themselves have potential risks. It is important that these contracts have unambiguous wording, particularly where there are pain/gain provisions.
Despite the name ‘guaranteed maximum price’ the client should still ensure that they have an adequate contingency.
[edit] Related articles on Designing Buildings
- Construction contracts.
- Construction manager at-risk.
- Contingency.
- Contract sum.
- Design and build.
- Fixed price contract.
- Guaranteed maximum price with target cost.
- Force account work.
- Loss and expense.
- Lump sum contract - pros and cons.
- Modifying clauses in standard forms of contract.
- Price.
- Procurement route.
- Provisional sum.
- Relevant event.
- Target cost contract.
- Time and material contract (T&M).
Featured articles and news
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.