Guaranteed maximum price for construction contracts
A guaranteed maximum price (GMP) is a form of agreement with a contractor in which it is agreed that the contract sum will not exceed a specified maximum.
Typically, this is a mechanism used on design and build contracts where the contractor has responsibility for completing the client’s design and for carrying out the construction works, so they are in a good position to control costs.
If the actual cost of the works is higher than the guaranteed maximum price, then the contractor must bear the additional cost. If the cost is lower than the guaranteed maximum price, then the contract should set out whether the savings made go to the client, to the contractor or are shared. This can create a ‘pain/gain’, or a target cost agreement, where the contractor is incentivised to make savings, but the client has the security of a cost cap.
Effectively, this sort of contract transfers risks for delivering the project from the client to the contractor. For example, if events such as exceptionally adverse weather or strikes occur, or if items that might otherwise have been the subject of provisional sums (such as complex groundworks, the nature of which cannot be determined until the ground is opened up), which on other forms of contract might have resulted in a claim by the contractor for loss and expense, on a guaranteed maximum price contract, the contractor has to bear any additional costs.
As a consequence the contractor is likely to tender a higher price. Effectively they price the risks that they are taking on. This may be acceptable to the client if their priority is certainty rather than the lowest possible cost, for example, if the client has fixed funding available that cannot be exceeded.
However, a guaranteed maximum price is not a panacea, and the price is not necessarily fixed. If the client requests ‘extras’, for example, if the scope of the works increases, then the contract must provide for the price to be increased. Similarly, if work is omitted, then the price should be reduced.
There is obviously scope here for disagreement about what constitutes a change that should result in a price adjustment, and there is the potential for the contractor to use the valuation of changes to recover costs they have incurred elsewhere. This can cause tension in a form of contract that was selected to provide certainty.
In deciding whether to seek a guaranteed maximum price, the client should assess the nature of the project, the likely risks and whether it is sensible to expect the contractor to bear those risks. If risks are priced by the contractor, but then do not transpire, the client will have paid for nothing, whilst if serious unforeseen problems are encountered, the contractor may attempt to find a way out of their obligation, or may be at risk of insolvency.
Whilst a simple project on a greenfield site might be suitable for a guaranteed maximum price, works to existing, older properties, or complex projects with inherent uncertainty (in particular in relation to ground works) might not. To assess these risks, it is important to ensure that proper investigations are undertaken and a fair apportionment of risks made. It is also important to ensure the client’s requirements have been clearly defined to avoid potential dispute about the nature of the works. A guaranteed maximum price is not an excuse to leap into the unknown and hope for the best.
Guaranteed maximum price contracts tend to be either bespoke (on small projects, often written by the contractor, and so potentially including hidden get-out clauses), or modified standard form contracts – which themselves have potential risks. It is important that these contracts have unambiguous wording, particularly where there are pain/gain provisions.
Despite the name ‘guaranteed maximum price’ the client should still ensure that they have an adequate contingency.
[edit] Related articles on Designing Buildings
- Construction contracts.
- Construction manager at-risk.
- Contingency.
- Contract sum.
- Design and build.
- Fixed price contract.
- Guaranteed maximum price with target cost.
- Force account work.
- Loss and expense.
- Lump sum contract - pros and cons.
- Modifying clauses in standard forms of contract.
- Price.
- Procurement route.
- Provisional sum.
- Relevant event.
- Target cost contract.
- Time and material contract (T&M).
Featured articles and news
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
























Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.