Outturn cost
The term ‘outturn’ or ‘out-turn’ refers to an amount achieved in a certain time, for example, an actual amount produced, or actual sales made. This is in contrast with the amount that might have been predicted or estimated. It is thought to be derived from, or related to, the term ‘turn out’.
The ‘outturn cost’ or ‘out-turn cost’ of a project is its actual construction cost. Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
This meaning of outturn cost is slightly confused by the use of terms such as ‘forecast outturn cost’, ‘estimated outturn cost’ or ‘target outturn cost’ which refer to the cost that is anticipated or should be achieved at the end of the project.
According to the Royal Institution of Chartered Surveyors (RICS), these outturn cost comprises: fixed costs, variable costs, variations, fluctuations and risk allowances.
- Fixed costs are costs that have been pre-calculated and agreed to be paid.
- Variable costs include; provisional sums, provisional quantities, prime cost sums and daywork allowances.
- Variations are alterations in the form of additions, substitutions or omissions from the original scope of works.
- Fluctuations are a way of dealing with inflation on large projects that may last for several years. The contractor is asked to tender based on current prices (prices at an agreed base date) and they are then reimbursed for price changes to specified items over the duration of the project (a fluctuating price).
- Risk allowances are financial allowances for works or services that are unknown in terms of quantity and specification, and are the client’s risk.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines out-turn cost (‘final account’, ‘actual cost’ or ‘cost outcome’) as: ‘The known cost at the end of a project. Generally, it refers to the actual, total construction cost calculated at the end of the project, which includes the effects of any changes made to the design and the impact of any disruption. It may also refer to the costs incurred over a defined period, such as in life cycle cost.’
See also: Final account.
[edit] Related articles on Designing Buildings
- Balance sheet.
- Bill of quantities BOQ.
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Contract conditions.
- Contract sum.
- Cost plans for construction projects.
- Cost reporting.
- Cost Value Reconciliations (CVR).
- Disallowed cost.
- Discounted cash flow.
- Elemental cost plan for design and construction.
- Final account.
- Prime cost sum.
- Quantity surveyor.
- Sunk cost.
- Types of cost.
[edit] External references
Featured articles and news
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.