Outturn cost
The term ‘outturn’ or ‘out-turn’ refers to an amount achieved in a certain time, for example, an actual amount produced, or actual sales made. This is in contrast with the amount that might have been predicted or estimated. It is thought to be derived from, or related to, the term ‘turn out’.
The ‘outturn cost’ or ‘out-turn cost’ of a project is its actual construction cost. Generally this refers to the actual, total construction cost calculated at the end of the project, but it may also refer to the cost of a specific contract, or to costs incurred over a defined period. This contrasts with cost estimates, or target costs, which are calculations of the cost that is expected, or the cost that should be achieved.
This meaning of outturn cost is slightly confused by the use of terms such as ‘forecast outturn cost’, ‘estimated outturn cost’ or ‘target outturn cost’ which refer to the cost that is anticipated or should be achieved at the end of the project.
According to the Royal Institution of Chartered Surveyors (RICS), these outturn cost comprises: fixed costs, variable costs, variations, fluctuations and risk allowances.
- Fixed costs are costs that have been pre-calculated and agreed to be paid.
- Variable costs include; provisional sums, provisional quantities, prime cost sums and daywork allowances.
- Variations are alterations in the form of additions, substitutions or omissions from the original scope of works.
- Fluctuations are a way of dealing with inflation on large projects that may last for several years. The contractor is asked to tender based on current prices (prices at an agreed base date) and they are then reimbursed for price changes to specified items over the duration of the project (a fluctuating price).
- Risk allowances are financial allowances for works or services that are unknown in terms of quantity and specification, and are the client’s risk.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki:
- Balance sheet.
- Bill of quantities BOQ.
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Contract conditions.
- Contract sum.
- Cost plans for construction projects.
- Cost reporting.
- Cost Value Reconciliations (CVR).
- Disallowed cost.
- Discounted cash flow.
- Elemental cost plan for design and construction.
- Final account.
- Prime cost sum.
- Quantity surveyor.
- Sunk cost.
- Variations.
[edit] External references
- RICS - Cost reporting
Featured articles and news
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Neuroscience for project success
Why people behave as they do. APM book.