Nominated supplier
In the construction industry, ‘supplier’ is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Typically, a contractor is able to purchase from their own choice of supplier, as long as they comply with the requirements set out in the specification. However, under certain circumstances, the client may wish to impose (or nominate) a particular supplier on the main contractor after the main contractor has been appointed.
The client may wish to use a particular supplier because:
- A particular product brand is required.
- The particular goods provided by the supplier are not widely available.
- There is an existing relationship with the supplier.
- Long delivery items are required where ordering is necessary before the appointment of a main contractor.
- Specialist design input is required in the early stages of design development.
- Complex or specialist industrial plant or equipment may be required, upon which the design will be based.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs. This allows the client to have direct separate negotiations with suppliers and feed their appointment into the contract after works by the main contractor have commenced.
A potential drawback of nominating a supplier is that the contractor is then not able to ‘shop around’ to obtain the best price or supplier. It is important therefore that suppliers are nominated with due consideration to their ability to supply in line with the project specification, programme and budget.
In addition, as the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for their failure to perform. However, as the supply contract is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated supplier to guarantee performance and indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
The complexity of this situation means that some forms of contract no longer include provision for the nomination, preferring to 'name' suppliers instead.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 2 June
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.

















