Nominated supplier
In the construction industry, ‘supplier’ is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Typically, a contractor is able to purchase from their own choice of supplier, as long as they comply with the requirements set out in the specification. However, under certain circumstances, the client may wish to impose (or nominate) a particular supplier on the main contractor after the main contractor has been appointed.
The client may wish to use a particular supplier because:
- A particular product brand is required.
- The particular goods provided by the supplier are not widely available.
- There is an existing relationship with the supplier.
- Long delivery items are required where ordering is necessary before the appointment of a main contractor.
- Specialist design input is required in the early stages of design development.
- Complex or specialist industrial plant or equipment may be required, upon which the design will be based.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs. This allows the client to have direct separate negotiations with suppliers and feed their appointment into the contract after works by the main contractor have commenced.
A potential drawback of nominating a supplier is that the contractor is then not able to ‘shop around’ to obtain the best price or supplier. It is important therefore that suppliers are nominated with due consideration to their ability to supply in line with the project specification, programme and budget.
In addition, as the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for their failure to perform. However, as the supply contract is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated supplier to guarantee performance and indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
The complexity of this situation means that some forms of contract no longer include provision for the nomination, preferring to 'name' suppliers instead.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Cumbria's vernacular architecture
A history of building impeded by unsettled times.
CIOB and MMC Ireland announce strategic partnership
For better working conditions, and a more productive construction sector.
More than just glass.
Grenfell Phase 2 final report for construction, at a glance
Twenty-three key issues raised and their recommendations.
Industry responds to the final Grenfell inquiry phase 2 report
Construction body responses to the long-awaited 7 volumes.
Chief construction advisers in brief
From July 2008 to November 2015.
The Grenfell phase 2 final report key summary points
And recommendations for the construction industry.
Approved Document B: Fire Safety upcoming updates
Including sprinklers in care homes, National classes and Fire resistance.
CIOB Podcast: 21st Century Construction
Catch up on the many previous episodes.
Tools and processes supporting a robust golden thread
BSRIA Handover Information and O&M Manuals guidance.
Industry survey highlights persistent skills gap
Building engineering business survey by ECA in partnership with BESA, SELECT and SNIPEF.
IHBC Conservation Professional Practice Principles
Spotlighted in HEF Historic Environment Overview.
CIAT collaborates with CIOB, CIfA, Icon to launch The Arc
Helping clients find specialist historic environment professionals.
Government building safety remediation data releases
Show some progress, but a 50% gap not yet started.
Testing For A Safer Future; an initial industry response
A response to the Independent Review of the Construction Product Testing Regime.
Requirements for UK buildings in certain circumstances.