Nominated supplier
In the construction industry, ‘supplier’ is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Typically, a contractor is able to purchase from their own choice of supplier, as long as they comply with the requirements set out in the specification. However, under certain circumstances, the client may wish to impose (or nominate) a particular supplier on the main contractor after the main contractor has been appointed.
The client may wish to use a particular supplier because:
- A particular product brand is required.
- The particular goods provided by the supplier are not widely available.
- There is an existing relationship with the supplier.
- Long delivery items are required where ordering is necessary before the appointment of a main contractor.
- Specialist design input is required in the early stages of design development.
- Complex or specialist industrial plant or equipment may be required, upon which the design will be based.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add mark up and attendance costs. This allows the client to have direct separate negotiations with suppliers and feed their appointment into the contract after works by the main contractor have commenced.
A potential drawback of nominating a supplier is that the contractor is then not able to ‘shop around’ to obtain the best price or supplier. It is important therefore that suppliers are nominated with due consideration to their ability to supply in line with the project specification, programme and budget.
In addition, as the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for their failure to perform. However, as the supply contract is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated supplier to guarantee performance and indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
The complexity of this situation means that some forms of contract no longer include provision for the nomination, preferring to 'name' suppliers instead.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.