Supply chains in construction
The supply chain is the interconnected hierarchy of supply contracts necessary to procure a built asset. Managing the supply chain involves understanding the breakdown and traceability of products and services, organisations, logistics, people, activities, information and resources that transform raw materials into a finished product that is fit for its purpose.
Unlike the automotive industry, the construction industry has the particular difficulty that every building is different, a unique prototype, developed by a team of consultants, contractors and other suppliers that may never have worked together before and may never work together again.
To add to the complexity, different procurement systems place elements of supply chain management with varying disciplines and organisations.
On a 'traditional' building project, design consultants are first tier suppliers, working for the client, and the contractor has a supply chain of sub-contractors and specialist suppliers. On PFI or design and build projects, however, there may be just one first tier supplier (sometimes the contractor) and design consultants will work for them as part of their supply chain.
On large or complex projects, responsibility and performance may cascade down the supply chain to a plethora of suppliers sometimes unknown to management at the top of the chain. For more information see: Suppliers.
One of the problems in the construction industry is that the first and second tier of the supply chain typically sign up to fairly onerous agreements, but as the chain develops, so the contractual liabilities decrease until suppliers at the end of the chain are often not locked in at all.
The key to supply chain management is providing a strategy that aligns with the project programme. This starts at the design stage, scoping the work into packages. Early evaluation based on feedback from the supply chain can produce enormous cost benefits and value. Capacity and production capability in a market controlled by supply and demand are particularly significant if programme bottlenecks are to be avoided.
In recent years larger companies offering continuity in construction have taken an increasing interest in establishing relationships beyond direct, first tier suppliers. Framework contracts and partnering agreements have pioneered this approach, encouraging the involvement of selected suppliers at relatively early stages of projects while offering continuity of work. This has led to greater collaboration between lead designers and product designers to the advantage of all parties.
'Integrated supply team' describes the integration of the complete supply chain involved in the delivery of a project. This may include the main contractor, designers, sub-contractors, suppliers, facilities managers, and so on. The integrated supply team is particularly relevant on public projects that may follow private finance initiative (PFI), prime contracting or design and build procurement routes. Under these routes, the entire supply team may be appointed after the project brief has been prepared, often under just one contract rather than separate contracts with each individual company.
Supply chain integration (SCI): 'involves everyone in the supply chain working cooperatively and collaboratively, so that the collective effort effectively delivers the client’s requirements and avoids unnecessary work. SCI is about adding value to design and construction processes, improving time, cost, quality, health and safety and other outcomes.' Ref BIM Overlay to the RIBA Outline Plan of Work, published by the RIBA in 2012.
NB In June 2019, the Construction Leadership Council (CLC) published Future Skills Report, criticising extended supply chains and calling for more direct employment of labour. Mark Reynolds, chair of the CLC skills workstream said: “This important report clearly sets out the challenge the industry and our clients face and the actions that must be taken now to avoid significant skills shortages in the future. When we have seen projects with higher levels of direct employment the results are often better, the workforce more engaged and ultimately the client and end users are happier with the final product.”
[edit] Related articles on Designing Buildings
- 2021 Building Engineering Business Survey.
- Broken chain.
- BSI construction product identification system.
- CLC urges inclusion of fluctuations provisions in contracts.
- Collaborative practices.
- Collateral warranties.
- Contractor.
- Contractor vs supplier.
- Cyber resilience.
- Down payment chain.
- Fair payment practices.
- Fragmentation of the UK construction industry.
- Framework agreement.
- Green supply chain management.
- Integrated supply team.
- Named supplier.
- Onerous contract.
- Partnering.
- Reflections on 2021.
- Subcontractor vs supplier.
- Supply.
- Supply chain integration.
- Supplier.
- Supplier selection.
- Supply chain management.
- Vertical integration.
- What is causing the rise in steel prices?
Featured articles and news
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”