CLC urges inclusion of fluctuations provisions in contracts
Contents |
[edit] Introduction
On 7 July 2021, the Construction Leadership Council (CLC) called on those responsible for developing, agreeing and managing construction contracts to adopt fluctuations provisions to combat significant volatility in the market.
[edit] Recommendations
In an open letter to the industry, CLC co-chair Andy Mitchell said that following the challenges of COVID-19 in 2020/2021, the industry faced more obstacles in the form of the availability and pricing volatility of labour and materials.
He cited a range of factors coming together at the same time to present an "escalating challenge" to the sector, including: rising freight costs; a shortage of materials; a shortage of hauliers; transitioning from CE to UKCA marking with insufficient product testing capacity; and new EU-related immigration rules.
[edit] Time of transition
Mitchell said, "This volatility is likely to be something we must live with for a while to come and could have a significant impact on the time frames and delivery costs of many projects.
"Most forms of construction contract have standard provisions for managing volatility without the need to make contract amendments. These provisions, such as fluctuations provisions in JCT and NEC 4 Secondary X1, provide a means of collaboratively sharing the risks associated with this volatility. We have been fortunate enough to operate in a stable environment for a long time and these clauses have been seldom used. However, they are ideally suited to providing a means for managing the volatile period we are entering and therefore CLC strongly urge those responsible for developing, agreeing and managing contracts, existing and new, to consider adopting these provisions in their contracts."
He also noted that design changes were likely to be necessary as a result of product availability, creating contractual challenges in the process.
He added, "Again, the CLC would encourage a collaborative approach to be taken to managing these risks by considering actions such as allowing longer mobilisation and lead-in periods for contracts and including up-front ordering and payment to suppliers in order to secure manufacture and delivery slots for critical material resources.
"We know that we perform better as an industry when a collaborative and team-based approach is adopted. We also know that our industry is strong and is growing right now. We would therefore encourage you to consider this message and find ways to work together so that this growth opportunity is maximised, and a sustainable industry supply chain is maintained."
This article originally appeared on the CIAT website under the headline, 'CLC calls for adoption of fluctuations provisions in contracts'. It was published on 7 July 2021.
--CIAT
[edit] Related articles on Designing Buildings
- Alternative dispute resolution for construction ADR.
- CE marking in the construction industry.
- CIAT articles.
- CLC publishes guidance on COVID-19 impact for NEC4.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- Examining the 2021 construction materials shortage.
- Fluctuations in construction contracts.
- JCT.
- Materials shortage prompts extra planning,
- NEC 4.
- Onerous contract.
- Supply chains in construction.
- UKCA mark transition extension for construction products requested.
- What is causing the rise in steel prices?
[edit] External resources
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.