Contract amendment
A contract amendment is to a formal change or modification to the terms and conditions of an existing construction contract. This can be necessary to accommodate adjustments that may arise during the course of a project, for example:
- Changes in the scope of work to be performed, including additions, deletions, or modifications to the original project plans and specifications.
- Adjustments to the project timeline, which might include extending or shortening the completion date or adjusting intermediate milestones.
- Modifications to the contract price, which could involve increasing or decreasing the overall budget based on the changes to the scope of work or other factors. It can also include changes to the payment schedule.
- Substitutions or changes in materials, products, or workmanship specifications that were initially agreed upon.
- Adjustments to ensure the contract remains compliant with any new or updated laws, regulations, or standards that may come into effect during the project.
- Revisions to the allocation of risks and responsibilities between the parties involved, such as changes in insurance requirements or liability clauses.
- Changes to the methods and processes for resolving disputes, which could involve amending arbitration clauses, mediation procedures, or other conflict resolution mechanisms.
Contract amendments are typically documented through formal written agreements signed by all parties involved in the original contract. This documentation ensures that there is a clear, mutual understanding of the changes and helps prevent disputes related to misunderstandings or misinterpretations of the modifications.
See also: Variations.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change control procedure for building design and construction.
- Change order for construction contracts.
- Compensation event.
- Confirmation of verbal instruction.
- Contract sum.
- Extension of time EOT in construction contracts.
- How to prepare a claim for an extension of time.
- Loss and expense.
- Payment for extra work.
- Prime cost sum.
- Provisional sum.
- Relevant event.
- Relevant matter.
- Scope of work.
- Valuation of interim payments.
- Variations.
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.