Confirmation of verbal instruction
Construction contracts generally give the contract administrator the power to issue instructions to the contractor.
Broadly, instructions may be given:
- To vary the works
- To postpone the works.
- To remedy workmanship, goods or materials, and equipment which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
The contractor must comply with the instructions within certain limitations. They have the right to ‘reasonably object’ to an instruction, and instructions can only be given as empowered by the contract.
Generally, instructions must be made formally, in writing, following a procedure set out in the contract. However, it is common for contracts to allow instructions to be given verbally, for example during a meeting, a site visit, or in an emergency situation. In this case, either the contract administrator should then confirm the instruction in writing to the contractor, or the contractor should confirm the instruction in writing to the contract administrator. If the receiving party does not dissent from the written confirmation, then the instruction will take effect.
This confirmation is referred to as a confirmation of verbal instruction (CVI) or an oral confirmation sheet. The contract should set out the exact procedures and the timescales for issuing such an instruction and dissenting from it.
Contracts can be vague about the nature of such confirmations, other than that they should be given in writing. Generally they should include:
- Details of who it is issued by and who it issued to.
- The date.
- Details of the contract that permits the instruction.
- The number of the CVI.
- Details of the instruction.
- The signature of the party issuing the CVI.
It is sensible to send an instruction by recorded delivery, or to confirm its receipt in the minutes of subsequent meetings. On some projects, there may an automated system in place for capturing and managing CVI’s and other instructions.
If a formal procedure is not followed for confirming verbal instruction, there can be disputes about:
- Work that has not been done which the contract administrator believes have been agreed.
- Work that the contractor has done but the client does not wish to pay for.
- Whether the instruction has been given to the right person, by the right person.
- Whether the instruction is allowed under the contract.
- Whether it has been properly valued and the value agreed.
- Whether the consequences on the programme have been properly considered.
- Whether an extension of time should be awarded.
Some contracts may make it a condition precedent to works being carried out that instructions are issued in writing. However, this can put the contractor in a difficult position, and whether to proceed with the works or to wait for a written instruction may be a commercial rather than a legal decision.
It is important that any instruction it is given by the contract administrator, rather than, for example, by the client, otherwise the instruction may constitute a new contract.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Architect.
- Architects instruction
- Change control
- Compensation events.
- Contract administrator.
- Contract sum.
- Defects liability period.
- Defects.
- Extension of time.
- Instruction.
- Mediation.
- Oral variation to written contract.
- Provisional sums.
- Relevant event.
- Variations.
- Work instruction.
Featured articles and news
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.






















