Change control procedure for building design and construction
Changes to a project may have impacts on time, cost or quality. Broadly, the later in the development of the project that changes occur, the greater those impacts are likely to be.
At certain stages in the design process, a complete package of information will be provided for the client to approve. Once this approval has been given, a change control procedure may be introduced to ensure that the approved information is not changed without the express permission of the client.
The CIOB 'Code of practice for project management' (4th edition), defines change control as 'a process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed.'
Examples of stages where change control procedures might be introduced include:
- At the end of the concept design stage if the project is tendered at this stage (for example on a design and build project).
- At the end of the concept design stage when the project brief (and employer's information requirements) might be frozen.
- During the detailed design stage when the detailed design, technical design and specification are finalised.
- During the tender stage when the tender documentation has been prepared.
- When the contractor is appointed and any further changes may qualify as variations.
It is important that the need for changes is minimised. This can be done by:
- Undertaking thorough site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by stakeholders.
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Ensuring that designs are properly co-ordinated before tender.
It is common for the cost consultant to report on the estimated cost of changes and for the client to prioritise which changes are acceptable. The client may decide to fund additional costs from a design contingency. A change control procedure should clearly define the process by which changes are requested and approved and who is responsible for those processes, including:
- The reasons for the change.
- Who is requesting the change.
- The consequences of the change, including health and safety, time, quality, cost (and who will bear the cost).
- Proposals for mitigation of any consequences.
- The risks associated with the change.
- Alternatives to the proposed change.
- Time by which the change must be instructed.
There may then be:
- Client evaluation of whether the impact of the change is acceptable and whether the proposal provides value for money.
- Client instructions to the consultant team.
- Contract administrator instructions to the contractor.
The client may have to consider a number of requests for changes and may therefore need the appropriate information to be able to prioritise them relative to one another.
Change control procedures should be formally set out in a project quality plan to ensure that changes to controlled aspects of the project are referred for review to the right person at the right time and so that changes are properly documented and reflected in all project information.
NB In the context of the UK Building Safety Act, a change control plan is a structured process and documentation system implemented to manage changes to a building's design, construction, or management that may impact its safety or compliance with building regulations. The change control plan outlines procedures for assessing proposed changes, determining their potential impact on building safety, and ensuring that appropriate measures are taken to maintain or enhance safety standards. By implementing a change control plan, building owners and managers can ensure that any modifications to a building are carefully assessed, managed, and implemented to maintain or improve safety standards and compliance with building regulations, as mandated by the Building Safety Act.
[edit] Related articles on Designing Buildings
- Abortive work.
- Change control: a quality perspective.
- Change management.
- Common data environment.
- Condition Report.
- Construction industry knowledge standard.
- Cost control.
- Design freeze.
- Design chill.
- Document control.
- End of stage report.
- Gateways.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Project brief derogations.
- Milestones.
- Scope creep.
- Variation.
- Value engineering.
- Value management.
[edit] External references
- OGC guidance on managing changes to requirements.
- OGC Achieving Excellence Guide 3 - Project ProcurementLifecyclepage 21.
- RICS draft guidance note: Managing the design delivery (including an example project change notice).
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























Comments
How do i cite this article
Have a look at this https://www.designingbuildings.co.uk/wiki/Citing_an_article_on_Designing_Buildings