Abortive work in building design and construction
Abortive work (or abortive costs or abortive fees) refers to work that has been started or carried out, but is not needed, or is no longer needed, and will not form part of the final development. The work will be wasted.
Abortive work can occur at any stage of a project, relating to the tender process, the work of consultants or construction.
Abortive work can arise because of:
- Cancellation of a project or an element of a project.
- Failed or abortive tendering.
- A change of circumstances (for example a change in legislative requirements).
- Clarification of circumstances (for example the opening up of existing works, or below ground works).
- Refusal of planning permission or other approvals.
- Changes in requirements, such as budget, location, size and technical requirements.
- The work carried out was unauthorised.
- The work was not properly authorised.
- Mistakes or misunderstandings.
- Clashes resulting from poor co-ordination.
- Design changes during manufacture or construction.
- Changes required once the completed works have been seen.
- Procurement of redundant goods, materials, plant or personnel.
The occurrence of abortive work can be reduced by:
- Undertaking thorough site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by all stakeholders (including end users).
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Introducing change-control procedures at key stages, with progressive gateways at which the project is defined, agreed, a decision taken to proceed to the next stage and some aspects frozen.
- Applying for permissions as early as is practicable.
- Ensuring designs are properly co-ordinated before tender.
- Limiting the number of tenderers and the extent of the tender process (particularly for procurement routes such as the private finance initiative, or prime contracting for which tender costs can be very high) .
- Only tendering for work where the chance of success is high.
- Adopting quality assurance systems.
- Adopting assistive technologies such as building information modelling (BIM) to improve co-ordination.
- Frequent site inspections.
- Suspending the works while potential changes are assessed in order to minimise potential abortive works.
Where abortive work is carried out, the cost of those works will be allocated depending on the wording of the contract.
Very broadly, the costs may be borne by the client if the conditions set out in the contract have been met (sometimes referred to as abortive terms), if the client has accepted the risk for unknown items (such as ground conditions) or if there has been a breach of contract by the client.
Where a change has been instructed by the client in accordance with the contract that might result in abortive work, this may give rise to additions or deductions from the contract sum and may also (but not necessarily) require adjustment of the completion date.
Where the consultant or contractor has carried out unauthorised or non-compliant work, or they have accepted the risk for unknown items, they may bear the cost of abortive work.
[edit] Related articles on Designing Buildings Wiki
- Change control procedure
- Cost control.
- Remedial work.
- Scope creep.
- Variation.
- Value engineering.
- Value management.
[edit] External references
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Comments