Design freeze
The building design process resolves client requirements into a set of instructions for the construction of a building that satisfies those requirements. It is generally an iterative process in which the design becomes more detailed and more 'fixed' as the project progresses.
Very broadly, the later in the development of the project that changes occur, the greater the impacts on time, cost and quality. At certain stages in the design process therefore, packages of information are provided for client approval, and once this approval has been given, a change control procedure is introduced to ensure that the approved information is not changed without the express permission of the client. This is referred to as a 'design freeze'.
The CIOB Code of practice for project management 4th edition, suggests that the term 'design freeze' refers to:
Completion and client's final approval of the design and associated processes, i.e. no further changes are contemplated or accepted within the budget approved in the project brief. |
A design freeze may be applied to the entire project, or to a specific aspect of it. There may also be an interim stage referred to as a 'design chill' or 'part freeze'. During this stage, all aspects of the design may continue to evolve, but change controls are placed on any changes to issued design documents. Interim changes may still occur within particular aspects of the works, and when finalised and formally reviewed, they may be incorporated into the design.
Parts of a design can be chilled whilst permitting other aspects to continue to develop; for example, the civil aspects may be chilled, allowing M&E design to continue in the full knowledge that there will be no change to the structure.
For more information see: Design freeze: a quality perspective.
Change controls may be introduced:
- At the end of the concept design stage if the project is tendered at this stage (for example on a design and build project).
- At the end of the concept design stage when the project brief (and employer's information requirements) might be frozen.
- During the detailed design stage when the detailed design, technical design and specification are finalised.
- During the tender stage when the tender documentation has been prepared.
- When the contractor is appointed and any further changes may qualify as variations.
For more information see: Change control.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
ICE and BSI launch revised PAS 128 standard.
The revised standard for mapping underground utilities.
Launching the UK net zero carbon buildings standard.
Cross-industry steering group seeks support in delivery.
How to write an inspection and test plan.
Help us update process pieces from your field.
APM report explores existing practice.
Previous reflections on mental health with CIAT.
COVID-19 and the importance of mental wellbeing.
IHBC accreditation recognised by CSCS
As Professionally Qualified Person (PQP).
The Queens speech; bill by bill for 2022.
In order of relevance and with industry responses.
Mental Health awareness week, May 9-15.
Raising awareness of the impacts of loneliness.
Rapidly renewable materials and construction.
The list is growing, and in more ways than one.
Personal experiences of infrastructure maintenance issues.
We shouldn’t build new, If we can’t maintain what's built.
Mass timber: challenges and potential solutions.
Timber Accelerator Hub phase 1 report