CLC publishes guidance on COVID-19 impact for NEC4
In July 2021, guidance on how clients and construction firms can collaborate to avoid disputes related to the COVID-19 pandemic under NEC4 contracts was published. The Construction Leadership Council (CLC) in collaboration with NEC published joint guidance on dealing with - and accommodating - the impact of COVID-19 on work under NEC4 contracts.
The guidance adds to the suite of outputs from the CLC's Business Models: Contractual Best Practice group which has routinely called for strategic collaboration between clients and the supply chain to avoid systemic market failures and compromised project delivery.
The guidance focuses on the NEC4 Engineering and Construction Contract (ECC), although it can also be applied to the NEC4 Engineering and Construction Subcontract (ECS), NEC3 ECC and ECS, subject to some amends which are outlined within the guidance.
To help clients and the supply chain to collaborate, the joint guidance offers support in navigating a number of circumstances within the context of the COVID-19 pandemic, including:
- Act of prevention.
- Project manager's instructions.
- Compensation events.
- Evaluation of a COVID-19 related compensation event.
- Working areas.
- Resource utilisation.
- Dealing with risk on future contracts.
Steve Bratt, Chair of the CLC's Business Models Workstream, said, "Following previous guidance, CLC remained open to industry feedback, and this guidance was developed in response to a series of questions which were raised with regard to projects impacted by COVID-19 operating under NEC contracts.
"As industry continues to manage the challenges of COVID-19, we are becoming increasingly concerned that many outstanding disputes remain unresolved and much uncertainty exists with regard to future contracts. We are therefore keen to do all we can to ensure clients work with their supply chains to fairly and collaboratively manage the commercial risks caused by COVID-19. Safety is paramount, but collaborative risk sharing will ensure secure project delivery and a long-term sustainable industry.
"COVID-19, safe working procedures and wider disruption has presented all parties with unquantifiable and unmanageable risks and costs. Traditional behaviours, such as inappropriate risk transfer, will not only lead to a negative outcome on individual contracts but will almost certainly lead to systemic failure in a fragile market seeking to build back greener and better."
Peter Higgins, Chairman of the NEC4 Contract Board, said, "NEC is pleased to have worked with the Construction Leadership Council in preparing this advice on dealing with COVID related issues under NEC contracts. NEC has always been a contract focusing on the parties working together to achieve a successful contract, and this guidance will help in managing collaboratively the risks which have arisen from COVID-19."
This article originally appeared on the CIAT website. It was published on 27 July 2021.
--CIAT
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution for construction ADR.
- CIAT articles.
- CLC urges inclusion of fluctuations provisions in contracts.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- NEC3.
- NEC4.
[edit] External resources
Featured articles and news
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.