CLC publishes guidance on COVID-19 impact for NEC4
In July 2021, guidance on how clients and construction firms can collaborate to avoid disputes related to the COVID-19 pandemic under NEC4 contracts was published. The Construction Leadership Council (CLC) in collaboration with NEC published joint guidance on dealing with - and accommodating - the impact of COVID-19 on work under NEC4 contracts.
The guidance adds to the suite of outputs from the CLC's Business Models: Contractual Best Practice group which has routinely called for strategic collaboration between clients and the supply chain to avoid systemic market failures and compromised project delivery.
The guidance focuses on the NEC4 Engineering and Construction Contract (ECC), although it can also be applied to the NEC4 Engineering and Construction Subcontract (ECS), NEC3 ECC and ECS, subject to some amends which are outlined within the guidance.
To help clients and the supply chain to collaborate, the joint guidance offers support in navigating a number of circumstances within the context of the COVID-19 pandemic, including:
- Act of prevention.
- Project manager's instructions.
- Compensation events.
- Evaluation of a COVID-19 related compensation event.
- Working areas.
- Resource utilisation.
- Dealing with risk on future contracts.
Steve Bratt, Chair of the CLC's Business Models Workstream, said, "Following previous guidance, CLC remained open to industry feedback, and this guidance was developed in response to a series of questions which were raised with regard to projects impacted by COVID-19 operating under NEC contracts.
"As industry continues to manage the challenges of COVID-19, we are becoming increasingly concerned that many outstanding disputes remain unresolved and much uncertainty exists with regard to future contracts. We are therefore keen to do all we can to ensure clients work with their supply chains to fairly and collaboratively manage the commercial risks caused by COVID-19. Safety is paramount, but collaborative risk sharing will ensure secure project delivery and a long-term sustainable industry.
"COVID-19, safe working procedures and wider disruption has presented all parties with unquantifiable and unmanageable risks and costs. Traditional behaviours, such as inappropriate risk transfer, will not only lead to a negative outcome on individual contracts but will almost certainly lead to systemic failure in a fragile market seeking to build back greener and better."
Peter Higgins, Chairman of the NEC4 Contract Board, said, "NEC is pleased to have worked with the Construction Leadership Council in preparing this advice on dealing with COVID related issues under NEC contracts. NEC has always been a contract focusing on the parties working together to achieve a successful contract, and this guidance will help in managing collaboratively the risks which have arisen from COVID-19."
This article originally appeared on the CIAT website. It was published on 27 July 2021.
--CIAT
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution for construction ADR.
- CIAT articles.
- CLC urges inclusion of fluctuations provisions in contracts.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- NEC3.
- NEC4.
[edit] External resources
Featured articles and news
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.