CLC publishes guidance on COVID-19 impact for NEC4
In July 2021, guidance on how clients and construction firms can collaborate to avoid disputes related to the COVID-19 pandemic under NEC4 contracts was published. The Construction Leadership Council (CLC) in collaboration with NEC published joint guidance on dealing with - and accommodating - the impact of COVID-19 on work under NEC4 contracts.
The guidance adds to the suite of outputs from the CLC's Business Models: Contractual Best Practice group which has routinely called for strategic collaboration between clients and the supply chain to avoid systemic market failures and compromised project delivery.
The guidance focuses on the NEC4 Engineering and Construction Contract (ECC), although it can also be applied to the NEC4 Engineering and Construction Subcontract (ECS), NEC3 ECC and ECS, subject to some amends which are outlined within the guidance.
To help clients and the supply chain to collaborate, the joint guidance offers support in navigating a number of circumstances within the context of the COVID-19 pandemic, including:
- Act of prevention.
- Project manager's instructions.
- Compensation events.
- Evaluation of a COVID-19 related compensation event.
- Working areas.
- Resource utilisation.
- Dealing with risk on future contracts.
Steve Bratt, Chair of the CLC's Business Models Workstream, said, "Following previous guidance, CLC remained open to industry feedback, and this guidance was developed in response to a series of questions which were raised with regard to projects impacted by COVID-19 operating under NEC contracts.
"As industry continues to manage the challenges of COVID-19, we are becoming increasingly concerned that many outstanding disputes remain unresolved and much uncertainty exists with regard to future contracts. We are therefore keen to do all we can to ensure clients work with their supply chains to fairly and collaboratively manage the commercial risks caused by COVID-19. Safety is paramount, but collaborative risk sharing will ensure secure project delivery and a long-term sustainable industry.
"COVID-19, safe working procedures and wider disruption has presented all parties with unquantifiable and unmanageable risks and costs. Traditional behaviours, such as inappropriate risk transfer, will not only lead to a negative outcome on individual contracts but will almost certainly lead to systemic failure in a fragile market seeking to build back greener and better."
Peter Higgins, Chairman of the NEC4 Contract Board, said, "NEC is pleased to have worked with the Construction Leadership Council in preparing this advice on dealing with COVID related issues under NEC contracts. NEC has always been a contract focusing on the parties working together to achieve a successful contract, and this guidance will help in managing collaboratively the risks which have arisen from COVID-19."
This article originally appeared on the CIAT website. It was published on 27 July 2021.
--CIAT
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution for construction ADR.
- CIAT articles.
- CLC urges inclusion of fluctuations provisions in contracts.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- NEC3.
- NEC4.
[edit] External resources
Featured articles and news
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.