Set off in construction contracts
Set off (sometimes called contra charging) is a legal process by which party A defends a claim brought by party B, by A setting off in extinction or diminution of B’s claim, claims which A alleges against B.
For example:
- A client might reclaim the cost of water damage to their property caused by a contractor fitting out the floor above the damaged area.
- A contractor might set off costs against a sub-contractor that caused damage to finished work adjacent to the working area of the sub-contractor.
- In the case of late completion a client might set off the appropriate amount of liquidated and ascertained damages in accordance with the contract.
Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim.
Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Contractual set off will depend on the wording of the agreement between the parties. It is possible for contractual set off rights to extend to a wide range of different contracts, but the wording must be clear. Equitable set off arises by operation of law if there is sufficient proximity and connection between the parties (e.g. the same parties, site and project). A recent statement of the law of equitable set off is given in the Court of Appeal judgement in Geldof Metaalconstructie NV v Simon Carves Ltd [2010].
If a contracting party becomes insolvent, the Insolvency Act 1986 Section 323 (bankruptcy) and the Insolvency Rules Rule 4.90 (liquidation) provide for a statutory set off known as ‘mutual credits and mutual debits’.
This statutory set off requires account to be taken between the insolvent party and the proving creditor of mutual debts, mutual credits and mutual dealings arising before the insolvency which are then set off leaving only the balance, if any, provable in the insolvency. This is, of course, only fair as otherwise the creditor would be 100% liable on debts due to the insolvent and only receive the relevant distribution (often nothing) on debts owed by the insolvent.
In construction contracts, rights of set off and withholding payments are regulated by the Housing Grants, Construction and Regeneration Act 1996 Part II Section 111, amended, with effect from October 2011, by the Local Democracy, Economic Development and Construction Act 2009 Part 8 Section 144. These Acts regulate the contents and prescribed periods for 'pay less' notices which must be served if a party wishes to deduct sums from amounts otherwise due under the contract.
Adjudication procedures constrain the effect of set off to preserve the public policy of adjudication that it should be a relatively speedy interim solution. In M J Gleeson Group Plc v Devonshire Green Holding Ltd [2004], the court held that a respondent could not set off claims arising after the commencement of the adjudication to avoid payment of a sum awarded by the adjudicator.
See also Section 111 (4) Housing Grants, Construction and Regeneration Act.
[edit] Related articles on Designing Buildings Wiki
- Abatement.
- Adjudication.
- Alternative dispute resolution.
- Contract.
- Contract conditions.
- Counterclaim.
- Housing Grants, Construction and Regeneration Act.
- Liquidated and ascertained damages.
- Mediation.
- Scheme for Construction Contracts.
[edit] External references
Featured articles and news
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Comments